Inspection Status: Passed
Inspection History: TRSP - PIA - Curb Placement
| Date |
Description |
Inspector |
Results |
Comments |
| 06/20/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
Project is still a bit away from preparing, forming and pouring curb in the ROW. Survey stakes have only been placed. |
| 06/27/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
Densities are scheduled for Monday, June 30th at 8 AM. |
| 06/30/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
Approximately 9 yards of concrete was used to pour 200 linear feet of vertical curb type 2. Concrete cylinder samples were taken at time of pour. |
| 07/07/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
CEMEX delivered 6.0 yds of concrete for the curb returns on the far west and east driveways of the project |
| 07/08/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
On-site curb was poured and didn't fall within the PIA scope. It is on the far east end of the project. I spoke with the foreman, Jesse, and he shared they will be pouring the last return and two ADA ramps the next day at 8:30 AM. |
| 07/09/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
Concrete curb return was poured at the most east end of the project. Same mix used for ADA ramp was used. |