Permit: TD-DEV-1224-00336
Permit Details
Apply Date:
12/12/2024
Applicant:
Ashley Benjamin
Description:
Restricted Record - New Medical Office Building on existing lot
Permit Reviews
Permit Number - TD-DEV-1224-00336
Permit Status: Inspections
Permit Description: Restricted Record - New Medical Office Building on existing lot
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/03/2025 | DEVELOPMENT PACKAGE NEW v.2 | 02/18/2025 | REQUIRES RESUBMIT |
| 05/06/2025 | DEVELOPMENT PACKAGE NEW v.4 | 05/16/2025 | APPROVED |
| 12/12/2024 | DEVELOPMENT PACKAGE NEW v.1 | 12/20/2024 | REQUIRES RESUBMIT |
| 03/27/2025 | DEVELOPMENT PACKAGE NEW v.3 | 04/28/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TD-DEV-1224-00336
Permit Status: Inspections
Permit Description: Restricted Record - New Medical Office Building on existing lot
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/02/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-1224-00336
Permite Description: Restricted Record - New Medical Office Building on existing lot
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/30/2025 | SITE - SWPPP Correction Notice | N/A | Partial Pass | For the contractor that he needed to be in compliance with the dust control and keep the dust down at all times |
| 08/28/2025 | N/A | Partial Pass | contractor installed 4 inch conduit for electrical good to backfield the contractor that some density test for the trench backfill . Also informed the contractor that they need to keep Glenn Street clean. | |
| 10/22/2025 | N/A | Partial Pass | Planting is well underway, holes are being dug per plans, species and locations are good, trees are properly staked. Irrigation lines are at appropriate depths. | |
| 01/12/2026 | ENGR Paving | N/A | Partial Pass | 01/12/26 Access Rd. that runs East/West at S side of site. Subgrade densities comply and slopes and grading match change of plan approved by PDSD. As-Built changes will be submitted at end of project. Puddling in parking lot at SW of Access Rd where it connects at match line will be addressed with a curb cut at low point with swale at cut running downgrade to depressed area behind existing Tree. Okay to place ABC pending this fix for puddle at north end of parking lot. This depressed area was discussed and agreed to with GC and JW Civil representative. |
| 01/12/2026 | N/A | Partial Pass | 01/12/26 Access Rd. that runs East/West at S side of site. Subgrade densities comply and slopes and grading match change of plan approved by PDSD. Grade hubs sufficient. As-Built changes will be submitted at end of project. Puddling in parking lot at SW of Access Rd where it connects at match line will be addressed with a curb cut at low point with swale at cut running downgrade to depressed area behind existing Tree. Okay to place ABC pending this fix for puddle at north end of parking lot. |
|
| 01/12/2026 | SITE - Stormwater Follow-up | N/A | Re-inspection required | 01/12/25 BMP’s on site Silt Fence Wattle Concrete washout Stabilized Entrance/Trackout 3rd Party inspections up to date. Wattle/Siltfence needs to be placed west of Trackout onto Glenn along fence-line to New Hospital Rd. Glenn needs protection between Trackout and corner of New Hospital with BMP. There is disturbed dirt and stockpiles upgrade from Glenn that needs to be protected. Concrete washout is full and needs to be emptied. |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-1224-00336
Permit Description: Restricted Record - New Medical Office Building on existing lot
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/11/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | Pre-con went well, contractor has a good understanding of what will be required. SWPPP board will be posted by our next meeting. | |
| 06/18/2025 | SITE - Stormwater Setup and Controls | Passed | Everything looks good right now and there’s no concerns |
Scheduled Inspections
Scheduled Inspections - TD-DEV-1224-00336
Status: Inspections
Description: Restricted Record - New Medical Office Building on existing lot
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 01/14/2026 | SITE - Stormwater Follow-up | Scheduled |
For information about today’s scheduled inspections please refer to the
PDSD Daily Inspections Dashboards (Desktop)
PDSD Daily Inspections Dashboards (Mobile)
.