Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Parcel: 110120900


Addresses:

5462 E GLENN ST


Inspection Status: Partial Pass

Inspection History: ENGR Paving

Permit Number - TD-DEV-1224-00336

Inspection Description - ENGR Paving

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/12/2026 ENGR Paving Partial Pass 01/12/26
Access Rd. that runs East/West at S side of site. Subgrade densities comply and slopes and grading match change of plan approved by PDSD. As-Built changes will be submitted at end of project. Puddling in parking lot at SW of Access Rd where it connects at match line will be addressed with a curb cut at low point with swale at cut running downgrade to depressed area behind existing Tree. Okay to place ABC pending this fix for puddle at north end of parking lot. This depressed area was discussed and agreed to with GC and JW Civil representative.
01/14/2026 ENGR Paving Re-inspection required I will reinspect in the morning. Grading needs to be finished to Hubs that were put in before I can check depth of asphalt to curbs. Compaction testing needs to be done. Contractor will have ABC ready.
01/15/2026 ENGR Paving Partial Pass Okay to pave S Access Rd. Low point puddle will be mitigated fixed with basins and curb cuts later where road meets parking lot at far S W end.
Densities comply. Hubs and string line for depth okay.