Permit: TD-DEV-1224-00336

Parcel: 110120900


Addresses:

5462 E GLENN ST

Inspection Status: Re-inspection required

Inspection History: SITE - Stormwater Follow-up

Date Description Inspector Results Comments
01/12/2026 SITE - Stormwater Follow-up Re-inspection required 01/12/25

BMP’s on site
Silt Fence
Wattle
Concrete washout
Stabilized Entrance/Trackout

3rd Party inspections up to date.

Wattle/Siltfence needs to be placed west of Trackout onto Glenn along fence-line to New Hospital Rd. Glenn needs protection between Trackout and corner of New Hospital with BMP. There is disturbed dirt and stockpiles upgrade from Glenn that needs to be protected.

Concrete washout is full and needs to be emptied.
01/14/2026 SITE - Stormwater Follow-up Passed
01/26/2026 SITE - Stormwater Follow-up Passed 1/26/26
Last 3rd party inspection was on 1/23. It rained .5 inches in this area over the weekend. Last inspection was on 1/23. check back.
Otherwise BMP’s look good.
02/09/2026 SITE - Stormwater Follow-up Passed Site is in good condition, per 3rd party inspector: stockpile at Glenn entrance needs wattle and site needs a designated concrete washout with signage.
03/02/2026 SITE - Stormwater Follow-up Passed Site controls are in proper working condition.
SITE - Stormwater Follow-up Scheduled
10/22/2025 SITE - Stormwater Follow-up Passed Site stormwater controls are performing as desired. Recommend to stake toilets to prevent tip over.
11/06/2025 SITE - Stormwater Follow-up Passed Overall site is well maintained. Porta Potties should be staked down to prevent tip-over.
11/19/2025 SITE - Stormwater Follow-up Passed Site is good overall, west entrance rock is getting thin, recommend refreshing prior to rain event.
12/02/2025 SITE - Stormwater Follow-up Passed
12/15/2025 SITE - Stormwater Follow-up Passed Construction entrance moved to Glenn. Stockpiles on west side should have wattle if unused for extended periods.
12/29/2025 SITE - Stormwater Follow-up Passed Site is in good condition