Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History
Permit Number - TD-DEV-1224-00336
Inspection Description -
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/12/2026 | Partial Pass | 01/12/26 Access Rd. that runs East/West at S side of site. Subgrade densities comply and slopes and grading match change of plan approved by PDSD. Grade hubs sufficient. As-Built changes will be submitted at end of project. Puddling in parking lot at SW of Access Rd where it connects at match line will be addressed with a curb cut at low point with swale at cut running downgrade to depressed area behind existing Tree. Okay to place ABC pending this fix for puddle at north end of parking lot. |
||
| 08/28/2025 | Partial Pass | Contractors having the road test for density on the north and east side test results are good pass with 97+ | ||
| 09/12/2025 | Partial Pass | Driveway apron on Glenn: sub-grade and curbing are good, no issues for the development package. ROW will inspect later today. | ||
| 09/16/2025 | Partial Pass | General note: Tucson Water did some work on Glenn St and made a muddy mess is the road, this was not from activity on site. Photo attached. |