Permit: TD-DEV-1224-00334
Permit Details
Apply Date:
12/10/2024
Applicant:
Brittini Halula
Description:
RESTRICTED RECORD - 120 unit, 4-story, multi-family affordable housing project
Permit Reviews
Permit Number - TD-DEV-1224-00334
Permit Status: Inspections
Permit Description: RESTRICTED RECORD - 120 unit, 4-story, multi-family affordable housing project
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/11/2024 | DEVELOPMENT PACKAGE NEW v.1 | 12/19/2024 | REQUIRES RESUBMIT |
| 03/06/2025 | DEVELOPMENT PACKAGE NEW v.3 | 03/26/2025 | REQUIRES RESUBMIT |
| 06/04/2025 | DEVELOPMENT PACKAGE NEW v.5 | 06/11/2025 | APPROVED |
| 04/21/2025 | DEVELOPMENT PACKAGE NEW v.4 | 05/28/2025 | REQUIRES RESUBMIT |
| 12/19/2024 | DEVELOPMENT PACKAGE NEW v.2 | 01/24/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TD-DEV-1224-00334
Permit Status: Inspections
Permit Description: RESTRICTED RECORD - 120 unit, 4-story, multi-family affordable housing project
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/23/2025 | Prior to project being finalized applicant must provide copy of avigation easement requested by Tucson Airport Authority. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-1224-00334
Permite Description: RESTRICTED RECORD - 120 unit, 4-story, multi-family affordable housing project
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/30/2025 | N/A | Partial Pass | Grading progress on basins and PAAL is underway. | |
| 03/12/2026 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | no concerns at this time everything looks good |
| 04/08/2026 | N/A | Partial Pass | contractor installed 90 lineal feet of 30 inch HDPE north end of the project good to backfield | |
| 04/28/2026 | ENGR - Drainage Structures | N/A | Partial Pass | 24" HDPE. Last section of Pipe from STA 5 + 15.98. Upgrade to end of pipe at STA 9+83.79. Pipe is set with survey offsets and elevations nails in place. Slope along length is reasonably +/- .5% Joints look tight and correct. Sealant visible inside Basin joints to pipe. Trenching/Bedding is good okay to backfill. Submit density results to the portal. Note: Port a John’s will be staked for next inspection. |
| 09/24/2026 | Grading Progress ENGR | N/A | Partial Pass | Subgrade for 6 parking bays to far west of parking lot. Plan calls for 2" over 4" light duty Paving. Subgrade is too low for 4". Contractor will have to add additional 2" AB in order to get to correct depth for 90% of area. 6" AB with remainder +/-An inch. Ok to Place AB in these bays to get to 8" to top of curb. Submit Subgrade compaction tests to the portal. -Add rock or recondition track out for it to function correctly |
| 11/04/2026 | For trash and recycling enclosures | N/A | Partial Pass | Verified grout. |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-1224-00334
Permit Description: RESTRICTED RECORD - 120 unit, 4-story, multi-family affordable housing project
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/26/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
| 12/02/2025 | NPPO Pre-Construction | Passed | NPPO plan is good. | |
| 12/02/2025 | SITE - Stormwater Setup and Controls | Passed | Perimeter controls, track-out rock, and site posting are pending delivery. These will be in place prior to excavation. |