Permit Details

Status:
Inspections
Type:
Development Package
Address:
4940 S PARK AV
Address NEW:
4940 S PARK AV
Apply Date:
12/10/2024
Applicant:
Brittini Halula
Description:
RESTRICTED RECORD - 120 unit, 4-story, multi-family affordable housing project

Permit Reviews

Permit Number - TD-DEV-1224-00334
Permit Status: Inspections
Permit Description: RESTRICTED RECORD - 120 unit, 4-story, multi-family affordable housing project
Start Date Submittal Complete Date Status  
12/11/2024 DEVELOPMENT PACKAGE NEW v.1 12/19/2024 REQUIRES RESUBMIT Review Details
03/06/2025 DEVELOPMENT PACKAGE NEW v.3 03/26/2025 REQUIRES RESUBMIT Review Details
06/04/2025 DEVELOPMENT PACKAGE NEW v.5 06/11/2025 APPROVED Review Details
04/21/2025 DEVELOPMENT PACKAGE NEW v.4 05/28/2025 REQUIRES RESUBMIT Review Details
12/19/2024 DEVELOPMENT PACKAGE NEW v.2 01/24/2025 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TD-DEV-1224-00334
Permit Status: Inspections
Permit Description: RESTRICTED RECORD - 120 unit, 4-story, multi-family affordable housing project
Total Outstanding Activity Conditions - 1
Date Name
01/23/2025 Prior to project being finalized applicant must provide copy of avigation easement requested by Tucson Airport Authority.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TD-DEV-1224-00334
Permite Description: RESTRICTED RECORD - 120 unit, 4-story, multi-family affordable housing project
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
12/30/2025 N/A Partial Pass Grading progress on basins and PAAL is underway.
03/12/2026 SITE - Stormwater Follow-up N/A Complete (Recurring) no concerns at this time everything looks good
04/08/2026 N/A Partial Pass contractor installed 90 lineal feet of 30 inch HDPE north end of the project good to backfield
04/28/2026 ENGR - Drainage Structures N/A Partial Pass 24" HDPE. Last section of Pipe from STA 5 + 15.98. Upgrade to end of pipe at STA 9+83.79. Pipe is set with survey offsets and elevations nails in place. Slope along length is reasonably +/- .5% Joints look tight and correct. Sealant visible inside Basin joints to pipe. Trenching/Bedding is good okay to backfill. Submit density results to the portal.

Note: Port a John’s will be staked for next inspection.
06/29/2026 For trash and recycling enclosures N/A Partial Pass Add verts to ends of wall so there are 2 reinforced cells at both ends and 3 in the corners. Bond beam is correct, horizontal reinforceing good. Okay to grout up to bond beam of 4 Enclosures at grade. Contractor will wet set verts to continue up to top of wall for second lift. Current verts will not reach top. Reschedule this pregrout inspection for second lift. When ready to pour floor and bollards schedule this inspection so we can check reinforcing and slope of floor and bollards spacing.

Completed Inspections

Permit Status: Inspections
Permit Number: TD-DEV-1224-00334
Permit Description: RESTRICTED RECORD - 120 unit, 4-story, multi-family affordable housing project
Total Completed Inspections - 3
Date Description Inspector Results Comments
11/26/2025 PDSD Engineering Division Pre-Construction SITE Passed
12/02/2025 NPPO Pre-Construction Passed NPPO plan is good.
12/02/2025 SITE - Stormwater Setup and Controls Passed Perimeter controls, track-out rock, and site posting are pending delivery. These will be in place prior to excavation.