Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/09/2026 | Partial Pass | contractors installing 30 inch storm drain pipe from the basin on the south west corner headed north 180 lineal feet they installed over the weekend. | ||
| 03/11/2026 | Partial Pass | contractor is good to backfill the HPDE pipe 30 inches storm drain coming off of the basin on the north west corner gone north good to backfill another 120 feet | ||
| 04/07/2026 | Partial Pass | From 30" 45deg. elbow at Sta. 5+15.98 to catch basin at Sta. 6+94.97: trench location and dimensions are accurate, bedding sand is good, slope is good. | ||
| 04/08/2026 | Partial Pass | contractor installed 90 lineal feet of 30 inch HDPE north end of the project good to backfield | ||
| 04/09/2026 | Partial Pass | Contactor is good to backfill the 24 inch HDPE pipe and the reducer from the 30 inch south end of the building | ||
| 04/13/2026 | Partial Pass | contractor is placing bedding sand for 24” HDPE PIPE. 124 LF. on the north in of the project. |
||
| 04/14/2026 | Partial Pass | Contactor is good to backfill 24 inch HDPE pipe north of the building storm drain | ||
| 04/24/2026 | Not Ready | Still trenching. recall for inspection. |