Inspection History Details
Inspection Status: Partial Pass
Inspection History: Grading Progress ENGR
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/24/2026 | Grading Progress ENGR | Partial Pass | Subgrade for 6 parking bays to far west of parking lot. Plan calls for 2" over 4" light duty Paving. Subgrade is too low for 4". Contractor will have to add additional 2" AB in order to get to correct depth for 90% of area. 6" AB with remainder +/-An inch. Ok to Place AB in these bays to get to 8" to top of curb. Submit Subgrade compaction tests to the portal. -Add rock or recondition track out for it to function correctly |
|
| 10/09/2026 | Grading Progress ENGR | Partial Pass | verify compaction results. provide material tickets for AB -. north lot okay it place approved AB |