Permit: TD-DEV-1224-00334

Parcel: 14020002F


Addresses:

4940 S PARK AV

Inspection Status: Partial Pass

Inspection History: For trash and recycling enclosures

Date Description Inspector Results Comments
06/12/2026 For trash and recycling enclosures Partial Pass Okay to pour Enclosure footings.
06/29/2026 For trash and recycling enclosures Partial Pass Add verts to ends of wall so there are 2 reinforced cells at both ends and 3 in the corners. Bond beam is correct, horizontal reinforceing good. Okay to grout up to bond beam of 4 Enclosures at grade. Contractor will wet set verts to continue up to top of wall for second lift. Current verts will not reach top. Reschedule this pregrout inspection for second lift. When ready to pour floor and bollards schedule this inspection so we can check reinforcing and slope of floor and bollards spacing.