Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TD-DEV-1122-00029
Permit Details
Apply Date:
11/07/2022
Applicant:
Lisa Bowers
Description:
New Drive-thru restaurant building
Permit Reviews
Permit Number - TD-DEV-1122-00029
Permit Status: Inspections
Permit Description: New Drive-thru restaurant building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/10/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 08/26/2024 | REQUIRES RESUBMIT |
| 11/07/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 12/28/2022 | REQUIRES RESUBMIT |
| 04/30/2025 | DEVELOPMENT PACKAGE REVIEW v.3 | 05/20/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TD-DEV-1122-00029
Permit Status: Inspections
Permit Description: New Drive-thru restaurant building
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/06/2025 | Prior to final issuance - associated COM permit |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-1122-00029
Permite Description: New Drive-thru restaurant building
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/03/2026 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | N/A | Partial Pass | Call Directors good to pour the menu boards foundation |
| 01/07/2026 | Grading Progress ENGR | N/A | Not Ready | contractor needs regrade the drive-through area before placing AB. |
| 02/10/2026 | Consultation SITE | N/A | Partial Pass | 2/10/26 Footer for crash bar in drive through. Dimensions and reinforcement correct to stamped detail and location is correct to DP. Hole for footer is large/oversized due to previous footer being removed. Backfill in lifts and compact. Get a compaction report on the backfill. Contractor is at Risk. Permit for footer is not approved or issued. |
| 02/18/2026 | N/A | Not Ready | Rebar cage for flagpole has been displaced and is making ground contact in multiple places. Re-call inspection once corrected. | |
| 09/09/2025 | For trash and recycling enclosures | N/A | Partial Pass | 9/9/25 Bollards are now placed correctly. Mat for slab-dobies are being flipped for correct 3" spacing to the Subgrade. Slope on mat is correct. Okay to pour slab. Call is back out for Flatwork inspections(sidewalk, curb ramps and curbs). |
| 02/23/2026 | COT - ENGR - Signage Final | N/A | Not Ready | Handicap van accessible sign parking sign needs 7’ clear to finish grade. Detail A page 9. |
| ENGR Paving | N/A | Scheduled | ||
| N/A | Scheduled | |||
| ENGR Engineering Final | N/A | Scheduled |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-1122-00029
Permit Description: New Drive-thru restaurant building
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/12/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | Went over the specs needed for this site, handed out a proper trash enclosure detail and inspection sheet. NPPO and SWPPP no needed here. | |
| 02/09/2026 | Grading Progress ENGR | Passed | ||
| 02/23/2026 | For trash and recycling enclosures | Passed | ||
| 02/23/2026 | ENGR Grading Final | Passed | 2/23/26 Handicap area parking space and aisle are fixed and the rest of grade looks good. Drive through will and in front of refuse enclosure be 3" over 4". Parking spaces 2.5" over 4" Density testing is good. Reveals good. Okay to pave. |
|
| 02/23/2026 | Passed | |||
| 02/24/2026 | LAND Landscape Appearance & Function Final | Passed | Have As-Builts note new locations for Water Meters/Backflow preventer and pressure reducers and any other changes for final closeout. RFI Civil about the Grouted RipRap outlet swale shown at Water Harvesting Basin 1. This will be checked at the DP Final. |
Scheduled Inspections
Scheduled Inspections - TD-DEV-1122-00029
Status: Inspections
Description: New Drive-thru restaurant building
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 02/25/2026 | ENGR Paving | Scheduled | |
| 02/25/2026 | ENGR Engineering Final | Scheduled | |
| 02/25/2026 | Scheduled |
For information about today’s scheduled inspections please refer to the
PDSD Daily Inspections Dashboards (Desktop)
PDSD Daily Inspections Dashboards (Mobile)
.