Inspection Status: Not Ready
Inspection History: For trash and recycling enclosures
Permit Number - TD-DEV-1122-00029
Inspection Description - For trash and recycling enclosures
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/11/2025 | For trash and recycling enclosures | Not Ready | 7/11/25 Rebar verts need two #4 verts at the ends, otherwise they are correct. 3" clearance from the dirt is needed on the Horz and chairs or dobbies need to be used to support the reinforcing. No rebar in the dirt. Bollards footers are not dug yet. | |
| 07/16/2025 | For trash and recycling enclosures | Partial Pass | 7/16/25 2 bars are in at wall ends. Dobbie's are in. Okay to pour. Build wall in two lifts. Call us out at 4’ for pre-grout inspection. Build horizontal reinforcement to plan. |
|
| 08/14/2025 | For trash and recycling enclosures | Partial Pass | 8/14/25 Okay to grout. Wall is built to 6'. Weep holes are cut. Reinforcing is correct. Bond beam in place at top. Provide pictures of grout coming out of holes. Call us back out to look at mat for floor and bollards placement. Submit compaction test result for Subgrade under floor. |
|
| 09/03/2025 | For trash and recycling enclosures | Not Ready | 9/3/25 Slab not ready to pour. Holes for bollards are incorrect. Holes need to be 3' from subgrade per plan. |
|
| 09/04/2025 | For trash and recycling enclosures | Partial Pass | 09/19/25, bollards have been repaired and are at 3' deep from grade. | |
| 09/09/2025 | For trash and recycling enclosures | Partial Pass | 9/9/25 Bollards are now placed correctly. Mat for slab-dobies are being flipped for correct 3" spacing to the Subgrade. Slope on mat is correct. Okay to pour slab. Call is back out for Flatwork inspections(sidewalk, curb ramps and curbs). |