Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TD-DEV-0924-00273
Permit Details
Apply Date:
09/29/2024
Applicant:
Alex Pillion
Description:
RESTRICED ACCESS 84-Unit Multifamily Development
Permit Reviews
Permit Number - TD-DEV-0924-00273
Permit Status: Inspections
Permit Description: RESTRICED ACCESS 84-Unit Multifamily Development
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/30/2024 | DEVELOPMENT PACKAGE NEW v.1 | 10/30/2024 | REQUIRES RESUBMIT |
| 12/12/2024 | DEVELOPMENT PACKAGE NEW v.3 | 12/19/2024 | APPROVED |
| 05/13/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 05/19/2025 | APPROVED |
| 11/19/2024 | DEVELOPMENT PACKAGE NEW v.2 | 12/03/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TD-DEV-0924-00273
Permit Status: Inspections
Permit Description: RESTRICED ACCESS 84-Unit Multifamily Development
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/02/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0924-00273
Permite Description: RESTRICED ACCESS 84-Unit Multifamily Development
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/10/2025 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | There is no concerns at this time |
| 07/10/2025 | N/A | Partial Pass | contractor installed 30 inch HDP 70 feet two barrels good to backfill | |
| 07/15/2025 | ENGR - Drainage Structures | N/A | Partial Pass | 07/15/25, south east side drainage structure, standards have been met, rebar placement and forms pass, good to pour. |
| 11/06/2025 | For trash and recycling enclosures | N/A | Partial Pass | 11/6/26 Ok to grout second lift of refuse enclosures. Request inspections for refuge enclosure when rebar for floor and bollard footers are ready. Protect all storm drain inlets on site with waddle or other bmp. Use correct concrete cleanout, as well....And as part of the renewed 2025 GCP, the site plan needs to show the entire area including the leased lot for material lay down parking etc. |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0924-00273
Permit Description: RESTRICED ACCESS 84-Unit Multifamily Development
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/16/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
| 05/30/2025 | SITE - Stormwater Setup and Controls | Passed | On our first by-weekly we will need to see the rain gauge, report book and full set of SWPPP plans. Start your schedule from this date for your by-weekly inspections. | |
| 09/24/2025 | Consultation SITE | Passed | For the contractor, we didn’t look at TEP’s lines. But we will inspect the church once it gets onto private property. |