Permit: TD-DEV-0923-00390
Permit Details
Apply Date:
09/08/2023
Applicant:
Kappcon Inc. General Contractor
Description:
Revision 1- Restricted Record-Demolition of existing pool structures within existing public park and construction of new public pool, splashpad, and aquatics building.
Permit Reviews
Permit Number - TD-DEV-0923-00390
Permit Status: Issued
Permit Description: Revision 1- Restricted Record-Demolition of existing pool structures within existing public park and construction of new public pool, splashpad, and aquatics building.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/11/2023 | DEVELOPMENT PACKAGE NEW v.1 | 09/20/2023 | REQUIRES RESUBMIT |
| 11/12/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 12/10/2025 | APPROVED |
| 12/26/2023 | DEVELOPMENT PACKAGE NEW v.3 | 01/08/2024 | APPROVED |
| 09/25/2023 | DEVELOPMENT PACKAGE NEW v.2 | 12/07/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TD-DEV-0923-00390
Permit Status: Issued
Permit Description: Revision 1- Restricted Record-Demolition of existing pool structures within existing public park and construction of new public pool, splashpad, and aquatics building.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/08/2026 | Prior to final - needs review for requests for information, AS-Built will need to be submitted |
Outstanding Inspections
Permit Status: Issued
Permit Number: TD-DEV-0923-00390
Permite Description: Revision 1- Restricted Record-Demolition of existing pool structures within existing public park and construction of new public pool, splashpad, and aquatics building.
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/28/2025 | Grading Progress ENGR | N/A | Partial Pass | Stormwater harvesting areas are being worked on. Middle area where old islands were is being left at original elevation. Basin floor elevations are good where finished. Recommend a perc test sooner rather than later to ensure proper infiltration. |
| 07/08/2026 | ENGR Engineering Final | N/A | Not Ready | Pool(s) not complete: railings, plumbing, floor finish not installed. Sidewalk at front entrance has an elevation change of greater than half an inch. Open electric boxes on east wall by therapy pool. Fencing not complete. Landscaping not finished, any deviations from the plans will require an As-Built and letter from Parks & Rec outlining the changes. Picnic table under canopy on south side wobbles, could crush small toes. Parking lot is being replaced under a separate contract, this needs to be shown as an as-built before this permit can be closed. |
| 07/08/2026 | LAND Landscape Appearance & Function Final | N/A | Partial Pass | GSI areas in parking lots are complete per plans. Missing decomposed granite ground cover around buildings. New plants around building have not been installed, intent is to exclude these per Parks & Rec's desire, change will need to be noted in an As-Built accompanied by a letter from Parks starting the acceptance of deviation from plans. |
| 07/08/2026 | N/A | Partial Pass | Pedestrian circulation is in compliance with ADA requirements with the exception of the change in elevation listed below. Flatwork on north side of 'Aquatics Equipment Building' not complete. Sidewalk in front of 'Aquatics Facility Building' has a change in elevation of greater than 1/2", needs to be less than 1/4" or less than 1/2" with a beveled edge. |
Completed Inspections
Permit Status: Issued
Permit Number: TD-DEV-0923-00390
Permit Description: Revision 1- Restricted Record-Demolition of existing pool structures within existing public park and construction of new public pool, splashpad, and aquatics building.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/25/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | Pre-construction meeting is complete. Expectations for necessary Site Engineering inspections has been conveyed to contractors. Pertinent inspections for this project will be updated and provided to contractors. No NPPO for this project, next step will be Stormwater Initial Inspection. | |
| 07/02/2025 | SITE - Stormwater Setup and Controls | Passed | Initial SWPPP devices are in place per plans. Contractor will call in SWPPP inspections every two weeks and after rain events. | |
| 09/22/2025 | Consultation SITE | Passed | Site visit due to recent rain events. All stormwater measures are in place and working as necessary. | |
| 10/28/2025 | Passed | initial grading work is complete with hubs and stakes at appropriate locations. | ||
| 04/09/2026 | Grading Progress ENGR | Passed | GSI basins are graded correctly, small water harvesting basin on north side is cut. Current plan on east side behind aquatics equipment building does not allow 5% slope for 10 feet away from building foundation (as required by IBC 1804.4) |
Scheduled Inspections
Scheduled Inspections - TD-DEV-0923-00390
Status: Issued
Description: Revision 1- Restricted Record-Demolition of existing pool structures within existing public park and construction of new public pool, splashpad, and aquatics building.
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 08/23/2026 | SITE - Stormwater Follow-up | Scheduled |