Permit Review Detail
Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE NEW v.2
Permit Number - TD-DEV-0923-00390
Review Name: DEVELOPMENT PACKAGE NEW v.2
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/25/2023 | Commercial Plumbing | APPROVED | |||
| 12/06/2023 | External Reviewers - COT Parks & Recreation | APPROVED | TD-DEV-0923-00390 Mission Manor Park at 6100 S 12th Ave, Parcel 13801001D Regarding TD-DEV-0923-00390, City of Tucson Parks and Recreation has no additional requirements for the Development Plan. Regards, Joe Barr Project Manager Parks and Recreation | City of Tucson Joe.Barr@tucsonaz.gov main 520.837.2263 |
||
| 10/27/2023 | External Reviewers - Tucson Airport Authority | APPROVED | October 25, 2023 Planning and Development Services City of Tucson 201 North Stone Avenue Tucson, AZ. 85701 RE: TD-DEV-0923-00390, Demolition of existing pool structures within existing public park and construction of new public pool, splashpad, and aquatics building / 6100 S 12th Ave, Tucson, AZ 85706, Received September 29, 2023 To whom this may concern, Thank you for the opportunity to comment on TD-DEV-0923-00390, the development plan for the demolition of existing pool structures within existing public park and construction of new public pool, splashpad, and aquatics building at 6100 S 12th Avenue. This development is located in the N.E. quarter and S.E quarter of the N.E. quarter of Section 11, Township 15S, Range 13E, of the Gila and Salt River Meridian. The development site occupies parcel numbers 138-01-001D and 138-01-001E, covers approximately 37.73 ± acres, and is zoned as Residence Zone 1 (R-1). The nearest major roadway intersection is West Calle Ramona and South 12th Avenue, approximately 1000 feet to the northeast of the subject development. This site does lie within the Tucson International Airport avigation easement requirements and public disclosure area, FAA traffic pattern airspace, and FAA Part 77 airspace. The Tucson Airport Authority approves the proposed project and is not requiring a resubmittal. Please do not hesitate to contact me if you have any questions or concerns regarding this comment letter. I can be reached by email at srobidoux@flytucson.com or by telephone at 520- 573-4811. Respectfully, Scott Robidoux, C.M. Manager of Planning |
||
| 10/20/2023 | ROW Engineering Review | APPROVED | |||
| 10/23/2023 | ROW Engineering Review | NOT REQUIRED | |||
| 12/06/2023 | CDRC Post Review Express | PENDING ASSIGNMENT | |||
| 10/23/2023 | NPPO | REQUIRES RESUBMIT | See Landscape Comments. If you have any questions about these comments, I can be reached at Matthew.Carlton@tucsonaz.gov or 520-837-4988 |
||
| 10/24/2023 | Site Engineering | REQUIRES RESUBMIT | 1. As the disturbance is over an acre a SWPPP will be required. Please submit one with the next submittal. 2. Include a note on the utility plan that states "Utility Plan for Reference Only - A separate utility permit will be required for proposed utility work" 3. Include a note on the plans that states a separate structural wall permit will be required for the 8' fence proposed. Stephen Blood (520) 837-4958 Stephen.blood@tucsonaz.gov |
||
| 10/23/2023 | Site Landscape | REQUIRES RESUBMIT | PROJECT: MISSION MANOR PARK ACTIVITY NO. TD-DEV-0923-00390 ADDRESS/PARCEL: 6100 S 12TH AV ZONING: R-1 This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants, and water harvesting. Please resubmit revised drawings along with a detailed response letter, which states how all Landscape/NPPO Review Section comments are addressed. COMMENTS: 1. Ensure that Zoning, Engineering comments, and concerns are addressed before landscape section approval. 2. Provide the development package case number, TD-DEV-0923-00390, adjacent to the title block on all sheets. 2-06.4.3 3. Include an NPPO waiver form. An NPPO is required per UDC 7.7.3-B. A Native Plant Preservation Plan, Section 7.7.4, is required to be submitted or approved or a request for an exception from the Native Plant Preservation requirements approved in accordance with Sections 7.7.3.D.3 & .4 of the UDC and Admin. Manual Section 2-11.0.0 prior to Grading Plan approval. A site visit was performed on 10.21.2023 by Landscape/NPPO and no protected plants were located on-site, but please submit the form anyway. 4. Working under the assumption that the proposed turf on-site is to match existing, can something be done to minimize the amount going in, for example, several tress and d.g. in the area? 5. As parks are not inherently commercial entities and are large swaths of pervious surfacing like turf, the CRWH Plan requirements are not necessary. If you have any questions about these comments, I can be reached at Matthew.Carlton@tucsonaz.gov |
||
| 10/16/2023 | Site Zoning | REQUIRES RESUBMIT | PDSD TRANSMITTAL FROM: PDSD Zoning Review PROJECT: Mission Manor Park – New Pool & Splash Pad Development Package (1st Review) TD-DEV-0923-00390 TRANSMITTAL DATE: October 16, 2023 DUE DATE: October 25, 2023 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is September 24, 2024. CONTENT REQUIREMENTS 1. COMMENT: 2-06.4.3 – Provide the development package case number, TD-DEV-0923-00390, adjacent to the title block on all sheets. 2-06.4.7 - General Notes The following general notes are required. Additional notes specific to each plan are required where applicable. 2-06.4.7.A - Zoning and Land Use Notes 2. COMMENT: 2-06.4.7.A.4 – General Note 3 remove the reference to “CR-3” as it is not applicable to this site. If you have any questions about this transmittal, please contact Nicholas Martell at Nicholas.Martell@tucsonaz.gov. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package & detailed response letter. |
||
| 09/25/2023 | CDRC Application Completeness Express | REVIEW COMPLETED | |||
| 09/29/2023 | CDRC Review Coordinator Express | REVIEW COMPLETED | Review request email sent per ADOT and TAA; FYI email sent to PAG, USPS, SWG & TEP. | ||
| 10/13/2023 | External Reviewers - Arizona Department of Transportation (ADOT) | REVIEW COMPLETED | [EXTERNAL] Re: DUE OCT 25TH, 2023 /DEMOLITION OF EXISTING POOL STRUCTURES WITHIN EXISTING PUBLIC PARK AND CONSTRUCTION OF NEW PUBLIC POOL, SPLASHPAD, AND AQUATICS BUILDING./ TD-DEV-0923-00390 Jay Gomes CDRC Good Morning, ADOT has no comments on this DEV. Thank you for the opportunity to review. |
||
| 09/29/2023 | External Reviewers - Pima Association of Governments | REVIEW COMPLETED | FYI email sent per PAG, USPS, SWG & TEP | ||
| 09/29/2023 | External Reviewers - Southwest Gas | REVIEW COMPLETED | FYI email sent per PAG, USPS, SWG & TEP | ||
| 09/29/2023 | External Reviewers - Tucson Electric Power (TEP) | REVIEW COMPLETED | FYI email sent per PAG, USPS, SWG & TEP | ||
| 09/29/2023 | External Reviewers - United States Postal Service (USPS) | REVIEW COMPLETED | FYI email sent per PAG, USPS, SWG & TEP | ||
| 10/02/2023 | Fire New Construction | REVIEW COMPLETED | |||
| 09/26/2023 | OK to Submit - Zoning Fast | REVIEW COMPLETED |