Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
In Review
Type:
Development Package
Address NEW:
2937 N FLANWILL BL
Apply Date:
08/30/2023
Applicant:
Richard Macias
Description:
Rev 1 - Update to fence, started 05.01.2026 ** Multifamily expansion adding a community center and additional unit. We've been working with Pat Tapia and Andy Vera on the trash pick-up location as shown on plan.

Permit Reviews

Permit Number - TD-DEV-0823-00376
Permit Status: In review
Permit Description: Rev 1 - Update to fence, started 05.01.2026 ** Multifamily expansion adding a community center and additional unit. We've been working with Pat Tapia and Andy Vera on the trash pick-up location as shown on plan.
Start Date Submittal Complete Date Status  
06/22/2026 DEVELOPMENT PACKAGE NEW REVISION v.3 06/25/2026 REQUIRES RESUBMIT Review Details
05/14/2026 DEVELOPMENT PACKAGE NEW REVISION v.2 05/21/2026 REQUIRES RESUBMIT Review Details
03/14/2024 DEVELOPMENT PACKAGE NEW v.3 02/24/2025 APPROVED Review Details
12/15/2023 DEVELOPMENT PACKAGE NEW v.2 02/06/2024 REQUIRES RESUBMIT Review Details
05/01/2026 DEVELOPMENT PACKAGE NEW REVISION v.1 05/01/2026 REQUIRES RESUBMIT Review Details
07/23/2026 DEVELOPMENT PACKAGE NEW REVISION v.4 07/30/2026 APPROVED Review Details
08/30/2023 DEVELOPMENT PACKAGE NEW v.1 12/01/2023 REQUIRES RESUBMIT Review Details

Outstanding Inspections

Permit Status: In Review
Permit Number: TD-DEV-0823-00376
Permite Description: Rev 1 - Update to fence, started 05.01.2026 ** Multifamily expansion adding a community center and additional unit. We've been working with Pat Tapia and Andy Vera on the trash pick-up location as shown on plan.
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
08/24/2026 Consultation SITE N/A Partial Pass Consultation for landings and slopes needed for compliant sidewalks and general drainage questions etc... I will also clear up questions of needs required for EV parking and Accessible parking. Also Weep Screed clearances needed at entryway landings.
11/18/2026 N/A Partial Pass Bottom bond beam in place. Okay to grout 1st bond beam. Continue to build wall to top per wall detail. Schedule pregrout inspection when 2nd bond beam is in place prior to grouting. All grout will be vibrated.

Completed Inspections

Permit Status: In Review
Permit Number: TD-DEV-0823-00376
Permit Description: Rev 1 - Update to fence, started 05.01.2026 ** Multifamily expansion adding a community center and additional unit. We've been working with Pat Tapia and Andy Vera on the trash pick-up location as shown on plan.
Total Completed Inspections - 1
Date Description Inspector Results Comments
03/12/2026 PDSD Engineering Division Pre-Construction SITE Passed Inspections needed:

Grading
Paving
Flatwork/Sidewalk
Landscaping
Striping
Refuse Enclosure
Screen Walls- after Revision
Site Consutation- whenever needed

Documents

File Name Document Type  
CONFORMED SET TD-DEV-0823-00376.PDF DOCUMENTS VIEW
1_BLESSING THROUGH ACTION - DRAINAGE REPORT_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
TD-DEV-0823-00376 - 3 - DP_V3.PDF DOCUMENTS VIEW
TD-DEV-0823-00376 - 3 - DP_V3.PDF DOCUMENTS VIEW
TD-DEV-0823-00376 - 2 - DP_V2.PDF PLANS UNDER REVIEW VIEW
TD-DEV-0823-00376 - 2 - 1ST SUBMITTAL RESPONSE_V1.PDF PLANS UNDER REVIEW VIEW
TD-DEV-0823-00376 - 2 DRAINAGE_V2.PDF PLANS UNDER REVIEW VIEW
TD-DEV-0823-00376 - 2 - LANDSCAPE RESPONSE_V1.PDF PLANS UNDER REVIEW VIEW
TD-DEV-0823-00376 - 2 - PDMR_V1.PDF PLANS UNDER REVIEW VIEW
TD-DEV-0823-00376 - 2 - TSMR_V1.PDF PLANS UNDER REVIEW VIEW
2937.PDF DOCUMENTS VIEW
APPROVED DEVELOPMENT LETTER-MERGE.PDF DOCUMENTS VIEW
1_BLESSING THROUGH ACTION - DRAINAGE REPORT_V1.PDF PLANS UNDER REVIEW VIEW
1_BLESSING THROUGH ACTION - DP PLAN SET_V1.PDF PLANS UNDER REVIEW VIEW