Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
5500 S NOGALES HY
Apply Date:
01/17/2023
Applicant:
Cody Conca
Description:
DP Development Package for Fire Station No 14 T22PRE0244 Pre Application Submittal. Also Note the county has assign the address of 5500 South Nogales Highway to this property and the APN number for the lot is pending.

Permit Reviews

Permit Number - TD-DEV-0123-00109
Permit Status: Complete
Permit Description: DP Development Package for Fire Station No 14 T22PRE0244 Pre Application Submittal. Also Note the county has assign the address of 5500 South Nogales Highway to this property and the APN number for the lot is pending.
Start Date Submittal Complete Date Status  
06/27/2023 DEVELOPMENT PACKAGE NEW v.1 11/01/2023 APPROVED Review Details
03/23/2023 DEVELOPMENT PACKAGE REVIEW v.2 05/23/2023 REQUIRES RESUBMIT Review Details
01/18/2023 DEVELOPMENT PACKAGE REVIEW v.1 03/06/2023 REQUIRES RESUBMIT Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: TD-DEV-0123-00109
Permite Description: DP Development Package for Fire Station No 14 T22PRE0244 Pre Application Submittal. Also Note the county has assign the address of 5500 South Nogales Highway to this property and the APN number for the lot is pending.
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
12/23/2024 SITE - Stormwater Follow-up N/A Complete (Recurring) No concerns at this time
11/19/2024 Consultation SITE N/A Partial Pass inform the contractor he need to call in every two weeks biweekly for the swept and for any inspections away from the building that belong to the DP department. The walls that have been installed at this time has been inspected by building department. Also inform him that everything away from the building belong to the DP departmentlandscaping catch basins drainage. Basins will be doing the inspections, parking, lots, handicap, ramps, etc. be done by us.
06/25/2025 SITE N/A Canceled
05/30/2025 ENGR Grading Final N/A Partial Pass 05/30/25, All grades and pours look good to date, compaction test are coming in to meet spec.
12/23/2024 N/A Partial Pass Footings inspection on the south side of the site passed 12/23/24

Completed Inspections

Permit Status: Complete
Permit Number: TD-DEV-0123-00109
Permit Description: DP Development Package for Fire Station No 14 T22PRE0244 Pre Application Submittal. Also Note the county has assign the address of 5500 South Nogales Highway to this property and the APN number for the lot is pending.
Total Completed Inspections - 12
Date Description Inspector Results Comments
06/14/2024 PDSD Engineering Division Pre-Construction SITE Passed
02/18/2025 SITE - Stormwater Follow-up Passed No issues at this time
05/08/2025 Consultation SITE Passed It was found that the NPPO inspection had never been completed holding up all other inspections. Compaction test to date have been received. Final grade inspections need to be done prior to any final concrete or paving is completed.
05/08/2025 COT - ENGR - Stormwater Passed
05/09/2025 NPPO Pre-Construction Passed 1 cactus to move, barrel.
05/15/2025 SITE - Stormwater Setup and Controls Passed
06/25/2025 For trash and recycling enclosures Passed Trash enclosure is completed other than paint on doors and holes drilled for lock downs on doors, this can be seen at final.
09/05/2025 PDSD Site/Engineering Division - Landscaping Passed 100 lb pressure test hold for 24 hours
09/05/2025 ENGR Grading Final Passed
09/05/2025 Passed All walls are completed and passed
12/22/2025 Final inspection to ensure all landscape and water harvesting SITE Passed Water harvesting basins are complete in accordance with approved plans.
12/30/2025 ENGR Engineering Final Passed