Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: For trash and recycling enclosures
| Date |
Description |
Inspector |
Results |
Comments |
| 06/13/2025 |
For trash and recycling enclosures |
|
Partial Pass |
6/13/25 Slab being poured is a large area in front of enclosure with fiber reinforcement. Included in that pour is the refuse enclosure apron. #4 @12" e.w. Slab "6 thick. Spacing correct, clearance correct. Okay to pour. |
| 06/25/2025 |
For trash and recycling enclosures |
|
Passed |
Trash enclosure is completed other than paint on doors and holes drilled for lock downs on doors, this can be seen at final. |