Inspection Status: Partial Pass
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 05/09/2025 |
ENGR Grading Final |
|
Partial Pass |
05/09/25, Southwest side of garage entry. 100 x 30 |
| 05/15/2025 |
ENGR Grading Final |
|
Partial Pass |
05/15/25, Southwest side of garage on the north side is ready to pour. 100 x 30 |
| 05/22/2025 |
ENGR Grading Final |
|
Partial Pass |
05/22/25, South driveline compaction test received and passed, Concrete poor is to spec. |
| 05/30/2025 |
ENGR Grading Final |
|
Partial Pass |
05/30/25, All grades and pours look good to date, compaction test are coming in to meet spec. |
| 07/21/2025 |
ENGR Grading Final |
|
Partial Pass |
07/21/25, this will complete the grades on all drive and parking areas. |
| 09/05/2025 |
ENGR Grading Final |
|
Passed |
|