Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
6280 S SPRUCE GOOSE AV
Apply Date:
10/07/2025
Applicant:
Celina Rodriguez
Description:
Cielo Reserve 1383 SFR (Model master plan TC-MDP-0525-00298)

Permit Reviews

Permit Number - TC-MDP-1025-00616
Permit Status: Inspections complete
Permit Description: Cielo Reserve 1383 SFR (Model master plan TC-MDP-0525-00298)
Start Date Submittal Complete Date Status  
10/07/2025 SITE FROM MODEL PERMIT - SUBDIVISION v.1 10/17/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-1025-00616
Permit Status: Inspections complete
Permit Description: Cielo Reserve 1383 SFR (Model master plan TC-MDP-0525-00298)
Total Outstanding Activity Conditions - 4
Date Name
10/02/2025 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
10/02/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
10/09/2025 Post-Installed Anchor Inspection Report is required.
10/09/2025 Post-Tension Inspection Report is required.

Conditions

Permit Number - TC-MDP-1025-00616
Permit Status: Inspections complete
Permit Description: Cielo Reserve 1383 SFR (Model master plan TC-MDP-0525-00298)
Date Description Comments
10/17/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
10/02/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
10/22/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1025-00616
Permite Description: Cielo Reserve 1383 SFR (Model master plan TC-MDP-0525-00298)
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
10/28/2025 COT - RSPL - Sewer N/A Not Ready 10.28.2025
Not ready.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1025-00616
Permit Description: Cielo Reserve 1383 SFR (Model master plan TC-MDP-0525-00298)
Total Completed Inspections - 20
Date Description Inspector Results Comments
10/28/2025 COT - RSPL - Yard Water Line Passed 10.28.2025
Approved and holding under test, okay to backfill with shading materials.
10/28/2025 COT - RSPL - Rough Soil Passed 10.28.2025
Approved and holding under test, okay to backfill with shading materials.
11/04/2025 COT - RSBU - Excavation/Rebar/Zoning Passed 11-4-25: excavation/layout and reinforcement verified per plans. Okay for concrete placement.
11/04/2025 COT - RSBU - Preslab Passed 11-4-25: preslab,excavation/layout and reinforcement verified per plans. Okay for concrete placement.
11/13/2025 BULD - Electrical Clearance Passed 11-13-25: okay to energize panel. Eco clearance issued to TEP.
11/14/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 11-14-25: exterior clips/sheathing and framing approved.
11/14/2025 COT - RSBU - Roof Nailing Passed 11-14-25: roof inspection approved. Okay to dry-in roof.
12/02/2025 COT - RSPL - Gas Pressure Test Passed 12-2-25: gas pressure test approved.
12/03/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 12.3.25
Corrections made as requested - approved
12/03/2025 RSBU - Building Progress Passed
12/12/2025 COT - RSBU - Interior Shear Bracing Passed
12/16/2025 COT - RSPL - Sewer Passed 12/16/2025
Approved and holding under test to HCS with green tracer wire.
01/27/2026 COT - BULD - SWG Clearance Passed Clearance for Southwest Gas. 1/27/2026
02/04/2026 COT - RSEL - Electrical Final Passed 2.4.26
Approved
02/04/2026 COT - RSEL - Electrical Underground Passed 2.4.26
Approved
02/04/2026 COT - RSEL - Outdoor Lighting Passed 2.4.26
Approved
02/04/2026 COT - RSME - Mechanical Final Passed 2.4.26
Approved
02/04/2026 COT - RSPL - Plumbing Final Passed 2.4.26
Approved
02/04/2026 ENGR Engineering Final Passed Site is complete in accordance with approved plans.
02/04/2026 RSBU - Building Final Passed 2.4.26
Approved

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CIELO RESERVE - LOT 22 START_V1.PDF DOCUMENTS VIEW
CR 22 SIC-2025-10-06_V1.PDF DOCUMENTS VIEW