Inspection Status: Re-inspection required
Inspection History: RSBU - Building Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 12/02/2025 |
RSBU - Building Progress |
|
Re-inspection required |
12-2-25: ground all exterior metal pancake boxes, firefoam penetrations-any penetration stemming from an unconditioned space must be firefoamed, firefoam around electrical boxes at shear walls, seal vapor barrier above window in master bedroom, seal vapor barrier/tear north wall of bedroom 2, fix tears to flex at bedroom 2 & at den |
| 12/03/2025 |
RSBU - Building Progress |
|
Passed |
|