Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Address:
1931 W KING AV
Address NEW:
1931 W KING AV
Apply Date:
08/23/2024
Applicant:
Ana Chavez
Description:
Residential Model De La Cruz- (Model master plan TC-MDP-0623-01107)

Permit Reviews

Permit Number - TC-MDP-0824-00892
Permit Status: Complete
Permit Description: Residential Model De La Cruz- (Model master plan TC-MDP-0623-01107)
Start Date Submittal Complete Date Status  
01/14/2025 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.4 01/17/2025 REQUIRES RESUBMIT Review Details
01/21/2025 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.5 02/13/2025 APPROVED Review Details
02/13/2025 RESTAMP - RESIDENTIAL v.1 02/18/2025 APPROVED Review Details
08/26/2024 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 08/26/2024 REQUIRES RESUBMIT Review Details
08/27/2024 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 09/11/2024 REQUIRES RESUBMIT Review Details
11/06/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/07/2025 APPROVED Review Details
12/12/2024 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.3 01/06/2025 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-MDP-0824-00892
Permit Status: Complete
Permit Description: Residential Model De La Cruz- (Model master plan TC-MDP-0623-01107)
Date Description Comments
01/14/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
08/23/2024 Separate submittal to PC RWRD is required for new septic sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
08/23/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0824-00892
Permite Description: Residential Model De La Cruz- (Model master plan TC-MDP-0623-01107)
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
03/19/2025 COT - RSBU - Preslab N/A Re-inspection required 3/19/25: Reinforcement overlap must be 24" min, UFER ground not installed
04/03/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Partial Pass 4-3-25, partial pass-blocking at bathroom not done but will be inspected at intermediate inspection. Okay to continue with construction.
04/03/2025 COT - RSBU - Interior Shear Bracing N/A Not Ready 4-3-25, not ready.
08/18/2025 COT - RSPL - Yard Water Line N/A Canceled
10/13/2025 ENGR Engineering Final N/A Failed Accessible route slope is at 13%, needs to be max 5% w/o handrail, 8.33% with handrail.
03/14/2025 COT - RSPL - Rough Soil N/A Partial Pass 3/14/25: Plumbing underground per plans and under test. Ok to proceed with backfill. Shading required. tracer wire required on all plumbing underground outside of building. ensure gray water is installed at intermediates

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0824-00892
Permit Description: Residential Model De La Cruz- (Model master plan TC-MDP-0623-01107)
Total Completed Inspections - 17
Date Description Inspector Results Comments
03/20/2025 COT - RSBU - Preslab Passed
03/20/2025 COT - RSBU - Excavation/Rebar/Zoning Passed
04/03/2025 COT - RSBU - Roof Nailing Passed 4-3-25, roof nailing approved. Okay to dry in roof.
05/28/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
05/28/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
06/10/2025 COT - RSBU - Interior Shear Bracing Passed 4-3-25, not ready.
6/10/25: Jesens Evans has submitted a letter taking responsibility for missed interior shear bracing inspection. File is attached to permit card.
08/06/2025 BULD - Electrical Clearance Passed 8-6-25: panel okay to be energized. ECO clearance issued to TEP.
08/27/2025 COT - RSPL - Sewer Passed
08/27/2025 COT - RSEL - Grounding/Bonding Passed
09/08/2025 COT - RSPL - Yard Water Line Passed
10/07/2025 COT - RSEL - Electrical Final Passed 10.7.2025
Verified same day thermostat lowered to 48", main service panel labeled and plugged.
10/07/2025 COT - RSME - Mechanical Final Passed 10.7.2025
Verified same day thermostat lowered to 48", main service panel labeled and plugged.
10/07/2025 COT - RSPL - Plumbing Final Passed 10.7.2025
Verified same day thermostat lowered to 48", main service panel labeled and plugged.
10/07/2025 RSBU - Building Final Passed 10.7.2025
Verified same day thermostat lowered to 48", main service panel labeled and plugged.
01/15/2026 COT - RSEL - Electrical Underground Passed 01/15/2026
Already passed on 10/7/25.
01/15/2026 COT - RSEL - Outdoor Lighting Passed 01/15/2026
Already passed on 10/7/25.
01/15/2026 COT - RSPL - Rough Soil Passed 01/15/2026
Already passed on 10/7/25.

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL (SSRS).PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW