Permit: TC-MDP-0824-00892
Permit Details
Apply Date:
08/23/2024
Applicant:
Ana Chavez
Description:
Residential Model De La Cruz- (Model master plan TC-MDP-0623-01107)
Permit Reviews
Permit Number - TC-MDP-0824-00892
Permit Status: Complete
Permit Description: Residential Model De La Cruz- (Model master plan TC-MDP-0623-01107)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/14/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.4 | 01/17/2025 | REQUIRES RESUBMIT |
| 01/21/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.5 | 02/13/2025 | APPROVED |
| 02/13/2025 | RESTAMP - RESIDENTIAL v.1 | 02/18/2025 | APPROVED |
| 08/26/2024 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 08/26/2024 | REQUIRES RESUBMIT |
| 08/27/2024 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 09/11/2024 | REQUIRES RESUBMIT |
| 11/06/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/07/2025 | APPROVED |
| 12/12/2024 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.3 | 01/06/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-MDP-0824-00892
Permit Status: Complete
Permit Description: Residential Model De La Cruz- (Model master plan TC-MDP-0623-01107)
| Date | Description | Comments |
|---|---|---|
| 01/14/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 08/23/2024 | Separate submittal to PC RWRD is required for new septic sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 08/23/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0824-00892
Permite Description: Residential Model De La Cruz- (Model master plan TC-MDP-0623-01107)
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2025 | COT - RSBU - Preslab | N/A | Re-inspection required | 3/19/25: Reinforcement overlap must be 24" min, UFER ground not installed |
| 04/03/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Partial Pass | 4-3-25, partial pass-blocking at bathroom not done but will be inspected at intermediate inspection. Okay to continue with construction. |
| 04/03/2025 | COT - RSBU - Interior Shear Bracing | N/A | Not Ready | 4-3-25, not ready. |
| 08/18/2025 | COT - RSPL - Yard Water Line | N/A | Canceled | |
| 10/13/2025 | ENGR Engineering Final | N/A | Failed | Accessible route slope is at 13%, needs to be max 5% w/o handrail, 8.33% with handrail. |
| 03/14/2025 | COT - RSPL - Rough Soil | N/A | Partial Pass | 3/14/25: Plumbing underground per plans and under test. Ok to proceed with backfill. Shading required. tracer wire required on all plumbing underground outside of building. ensure gray water is installed at intermediates |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0824-00892
Permit Description: Residential Model De La Cruz- (Model master plan TC-MDP-0623-01107)
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/20/2025 | COT - RSBU - Preslab | Passed | ||
| 03/20/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 04/03/2025 | COT - RSBU - Roof Nailing | Passed | 4-3-25, roof nailing approved. Okay to dry in roof. | |
| 05/28/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 05/28/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 06/10/2025 | COT - RSBU - Interior Shear Bracing | Passed | 4-3-25, not ready. 6/10/25: Jesens Evans has submitted a letter taking responsibility for missed interior shear bracing inspection. File is attached to permit card. |
|
| 08/06/2025 | BULD - Electrical Clearance | Passed | 8-6-25: panel okay to be energized. ECO clearance issued to TEP. | |
| 08/27/2025 | COT - RSPL - Sewer | Passed | ||
| 08/27/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 09/08/2025 | COT - RSPL - Yard Water Line | Passed | ||
| 10/07/2025 | COT - RSEL - Electrical Final | Passed | 10.7.2025 Verified same day thermostat lowered to 48", main service panel labeled and plugged. |
|
| 10/07/2025 | COT - RSME - Mechanical Final | Passed | 10.7.2025 Verified same day thermostat lowered to 48", main service panel labeled and plugged. |
|
| 10/07/2025 | COT - RSPL - Plumbing Final | Passed | 10.7.2025 Verified same day thermostat lowered to 48", main service panel labeled and plugged. |
|
| 10/07/2025 | RSBU - Building Final | Passed | 10.7.2025 Verified same day thermostat lowered to 48", main service panel labeled and plugged. |
|
| 01/15/2026 | COT - RSEL - Electrical Underground | Passed | 01/15/2026 Already passed on 10/7/25. |
|
| 01/15/2026 | COT - RSEL - Outdoor Lighting | Passed | 01/15/2026 Already passed on 10/7/25. |
|
| 01/15/2026 | COT - RSPL - Rough Soil | Passed | 01/15/2026 Already passed on 10/7/25. |