Permit: TC-MDP-0524-00570
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
6116 E BLACK CAVIAR PL
Address NEW:
6116 E BLACK CAVIAR PL
Apply Date:
05/01/2024
Applicant:
Helen Ormsby
Description:
Blackhawk H30D Model Plan
Permit Reviews
Permit Number - TC-MDP-0524-00570
Permit Status: Inspections complete
Permit Description: Blackhawk H30D Model Plan
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/28/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 08/28/2025 | REQUIRES RESUBMIT |
| 05/02/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 05/13/2024 | APPROVED |
| 07/22/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/23/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-MDP-0524-00570
Permit Status: Inspections complete
Permit Description: Blackhawk H30D Model Plan
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/23/2025 | Post-Installed Anchor Inspection Report is required. |
Conditions
Permit Number - TC-MDP-0524-00570
Permit Status: Inspections complete
Permit Description: Blackhawk H30D Model Plan
| Date | Description | Comments |
|---|---|---|
| 05/13/2024 | The Contractor you have added to your permit cannot be verified. Please contact staff to have the ROC number added to the account. | |
| 05/08/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 05/01/2024 | Post-Tension Inspection Report is required. | |
| 05/01/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 05/01/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 05/08/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 05/08/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00570
Permite Description: Blackhawk H30D Model Plan
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/20/2025 | COT - RSBU - Roof Nailing | N/A | Re-inspection required | 6/17/25: trades shall not begin work prior to completion of framing inspection. 6/20/25: Fasteners at all shear walls not per plan, fasteners shall not be closer than 3/8" from edge of panels and shall not over penetrate more than 1/8" at osb and shall sit flush with face of thermoply, anchor bolts shall be no closer than 4" from edge of sill plate and no further than 12'' from edge, RSP4 spacing not per plan at west wall line, shearwall missing per plan at south west corner of house, shearwall length not per plant at south east corner plans call for 7', detail 36/SD4 not per plan at non-bearing shearwall below, Gabel end bracing not per plan, SD4/35 at master not per plan, shim interior load bearing wall at h2.5, loose roof panels at south east and north east. |
| 06/20/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Re-inspection required | 6/17/25: trades shall not begin work prior to completion of framing inspection. 6/20/25: Fasteners at all shear walls not per plan, fasteners shall not be closer than 3/8" from edge of panels and shall not over penetrate more than 1/8" at osb and shall sit flush with face of thermoply, anchor bolts shall be no closer than 4" from edge of sill plate and no further than 12'' from edge, RSP4 spacing not per plan at west wall line, shearwall missing per plan at south west corner of house, shearwall length not per plant at south east corner plans call for 7', detail 36/SD4 not per plan at non-bearing shearwall below, Gabel end bracing not per plan, SD4/35 at master not per plan, shim interior load bearing wall at h2.5, loose roof panels at south east and north east. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00570
Permit Description: Blackhawk H30D Model Plan
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/22/2025 | COT - RSPL - Rough Soil | Passed | 5-22-25: underground plumbing verified as per approved plans. Okay to backfill with shading materials. | |
| 05/22/2025 | COT - RSPL - Sewer | Passed | 5-22-25: HCS verified per plans. Okay to backfill with shading materials. | |
| 05/22/2025 | COT - RSPL - Yard Water Line | Passed | 5-22-25, main water line approved. Okay to backfill using shading materials. | |
| 06/04/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 6-4-25: preslab,excavation/reinforcement verified per plan. Okay to pour concrete. | |
| 06/04/2025 | COT - RSBU - Preslab | Passed | 6-4-25: preslab,excavation/reinforcement verified per plan. Okay to pour concrete. | |
| 06/04/2025 | COT - RSEL - Electrical Underground | Passed | 6-4-25: electrical underground approved. | |
| 06/20/2025 | BULD - Electrical Clearance | Passed | 6-4-25: missing address label on panel. Have Electrical Engineer/Architect of record submit a revision letter to the city documenting he/she authorizes the use of copper clad wires. 6/20/25: ECO TEP CLEARANCE |
|
| 06/26/2025 | COT - RSBU - Roof Nailing | Passed | ||
| 06/27/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 6/27/2025 approved. | |
| 07/09/2025 | COT - RSPL - Gas Pressure Test | Passed | 7-9-25: approved | |
| 07/11/2025 | COT - RSEL - Grounding/Bonding | Passed | 7-11-25: residential intermediate inspection approved. Okay to construction. | |
| 07/11/2025 | RSBU - Building Progress | Passed | ||
| 07/24/2025 | COT - RSBU - Interior Shear Bracing | Passed | 7.24.25 Fastener schedule at shear walls meets or exceed requirements. Ok to proceed. |
|
| 07/24/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 7.24.25 Intermediate verified and approved under "building progress, bonding" previously, see History for notes and ref. |
|
| 09/05/2025 | COT - BULD - SWG Clearance | Passed | 9.5.2025 Clearance for SW Gas. |
|
| 10/23/2025 | COT - RSEL - Electrical Final | Passed | ||
| 10/23/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 10/23/2025 | COT - RSME - Mechanical Final | Passed | ||
| 10/23/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 10/23/2025 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. Engineering is okay for CofO. | |
| 10/23/2025 | RSBU - Building Final | Passed |