Permit: TC-MDP-0224-00251
Permit Details
Apply Date:
03/05/2024
Applicant:
Daria Hopkins
Description:
SFR MERI132021 T21-M0062
Permit Reviews
Permit Number - TC-MDP-0224-00251
Permit Status: Issued
Permit Description: SFR MERI132021 T21-M0062
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/17/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/18/2024 | APPROVED |
03/05/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 03/18/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0224-00251
Permit Status: Issued
Permit Description: SFR MERI132021 T21-M0062
Date | Description | Comments |
---|---|---|
03/18/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
03/18/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
03/18/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
03/18/2024 | Post-Installed Anchor Inspection Report is required. | |
03/18/2024 | Post-Tension Inspection Report is required. | |
02/23/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
02/23/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
03/18/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
03/18/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0224-00251
Permit Description: SFR MERI132021 T21-M0062
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/09/2024 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 9/8/2024 | |
08/09/2024 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading required. 9/8/2024 | |
08/09/2024 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 9/8/2024 | |
08/16/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
08/16/2024 | COT - RSBU - Preslab | Passed | ||
08/16/2024 | COT - RSEL - Electrical Underground | Passed | ||
08/16/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
09/09/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
09/09/2024 | COT - RSBU - Roof Nailing | Passed | ||
10/10/2024 | BULD - Electrical Clearance | Passed | 10/10/24: ECO TEP clearance | |
10/24/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 10-24-24-All items listed from previous inspection were corrected to match original plans. Intermediates approved-okay to continue construction. | |
10/24/2024 | COT - RSPL - Gas Pressure Test | Passed | 10-24-24 Gas pressure test approved. | |
11/08/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
12/23/2024 | COT - BULD - SWG Clearance | Passed | SWG clearance approved 12/23/ |