Permit: TC-COM-1124-02162
Permit Details
Apply Date:
11/11/2024
Applicant:
Dennis Caldwell
Description:
ELVIRA BUILDING 2721 TENANT IMPROVEMENT. NO CHANGE OF USE OR ADDITIONAL SF TO EXISTING BUILDING. +/-2087 SF OF OFFICE SPACE, RESTROOMS AND THE REST AS OPEN WAREHOUSE SPACE. 4 OVERHEAD DOORS POSITIONED AT NEW OPENINGS FOR NEW TRUCK DOCKS. MECHANICAL AND PLUMBING TO BE REWORKED TO FIT NEW PARTITION LAYOUT. NEW ELECTRICAL WORK TO INCLUDE POWER AND LIGHTING THROUGHOUT BUILDING.
Permit Reviews
Permit Number - TC-COM-1124-02162
Permit Status: Complete
Permit Description: ELVIRA BUILDING 2721 TENANT IMPROVEMENT. NO CHANGE OF USE OR ADDITIONAL SF TO EXISTING BUILDING. +/-2087 SF OF OFFICE SPACE, RESTROOMS AND THE REST AS OPEN WAREHOUSE SPACE. 4 OVERHEAD DOORS POSITIONED AT NEW OPENINGS FOR NEW TRUCK DOCKS. MECHANICAL AND PLUMBING TO BE REWORKED TO FIT NEW PARTITION LAYOUT. NEW ELECTRICAL WORK TO INCLUDE POWER AND LIGHTING THROUGHOUT BUILDING.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/26/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/26/2025 | APPROVED |
| 11/12/2024 | COMMERCIAL REVIEW - FULL v.1 | 12/10/2024 | REQUIRES RESUBMIT |
| 01/13/2025 | COMMERCIAL REVIEW - FULL v.2 | 02/04/2025 | REQUIRES RESUBMIT |
| 02/27/2025 | COMMERCIAL REVIEW - FULL v.3 | 03/27/2025 | APPROVED |
| 06/03/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 06/06/2025 | APPROVED |
| 03/27/2025 | RESTAMP - COMMERCIAL v.1 | 04/01/2025 | APPROVED |
| 09/03/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/08/2025 | APPROVED |
| 08/22/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/25/2025 | APPROVED |
| 08/13/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/14/2025 | APPROVED |
| 04/15/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 05/06/2025 | APPROVED |
Conditions
Permit Number - TC-COM-1124-02162
Permit Status: Complete
Permit Description: ELVIRA BUILDING 2721 TENANT IMPROVEMENT. NO CHANGE OF USE OR ADDITIONAL SF TO EXISTING BUILDING. +/-2087 SF OF OFFICE SPACE, RESTROOMS AND THE REST AS OPEN WAREHOUSE SPACE. 4 OVERHEAD DOORS POSITIONED AT NEW OPENINGS FOR NEW TRUCK DOCKS. MECHANICAL AND PLUMBING TO BE REWORKED TO FIT NEW PARTITION LAYOUT. NEW ELECTRICAL WORK TO INCLUDE POWER AND LIGHTING THROUGHOUT BUILDING.
| Date | Description | Comments |
|---|---|---|
| 08/14/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 11/12/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 08/14/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 04/15/2025 | Elevator -Special Inspections Intermediate Certificate | |
| 01/13/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 08/14/2025 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 11/12/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 01/21/2025 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1124-02162
Permite Description: ELVIRA BUILDING 2721 TENANT IMPROVEMENT. NO CHANGE OF USE OR ADDITIONAL SF TO EXISTING BUILDING. +/-2087 SF OF OFFICE SPACE, RESTROOMS AND THE REST AS OPEN WAREHOUSE SPACE. 4 OVERHEAD DOORS POSITIONED AT NEW OPENINGS FOR NEW TRUCK DOCKS. MECHANICAL AND PLUMBING TO BE REWORKED TO FIT NEW PARTITION LAYOUT. NEW ELECTRICAL WORK TO INCLUDE POWER AND LIGHTING THROUGHOUT BUILDING.
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/27/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | 8-27-25: not applicable |
| 07/10/2025 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Canceled | 7-10-25: inspection must be scheduled under development plan. |
| 05/14/2025 | COT - HCPL - Plumbing Progress | N/A | Re-inspection required | 5-14-25, plumbing progress inspection called in with no additional notes. Arrived on site at approximately 1135 hours. Called contractor at 1139 hours and received no answer. I waited until 1151 hours and left. |
| COT - FCON - Fire - Final | N/A | Not Ready | Need knox box and extinguishers installed. | |
| 07/07/2025 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | 7-7-25: insulate 3/4" copper lines-will be verified at finals. Electrical above ceiling approved-okay to continue with construction at progress areas. |
| 04/25/2025 | COT - HCEL - Electrical Intermediate | N/A | Re-inspection required | 4/25/25: electrical in wall not per approved plans |
| 09/09/2025 | COT - HCBU - CofO | N/A | Partial Pass | 9-9-25: building final approved. Okay for Level 4 TCO-See pending conditions. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1124-02162
Permit Description: ELVIRA BUILDING 2721 TENANT IMPROVEMENT. NO CHANGE OF USE OR ADDITIONAL SF TO EXISTING BUILDING. +/-2087 SF OF OFFICE SPACE, RESTROOMS AND THE REST AS OPEN WAREHOUSE SPACE. 4 OVERHEAD DOORS POSITIONED AT NEW OPENINGS FOR NEW TRUCK DOCKS. MECHANICAL AND PLUMBING TO BE REWORKED TO FIT NEW PARTITION LAYOUT. NEW ELECTRICAL WORK TO INCLUDE POWER AND LIGHTING THROUGHOUT BUILDING.
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/04/2025 | COT - HCPL - Rough Soil | Passed | ||
| 07/15/2025 | COT - HCBU - Framing | Passed | 7-15-25: approved | |
| 07/16/2025 | BULD - Electrical Clearance | Passed | 7-16-25: okay to energize-INCR issued to TEP. NOTE: ISSUED WRONG CLEARANCE BUT SPOKE WITH MARCIA-TEP & CHANGED TO AN ECO. 7-16-25 @ 1300 HOURS. |
|
| 08/27/2025 | COT - FCON - Alarm - Final | Passed | ||
| 08/27/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 8-27-25: approved | |
| 08/27/2025 | ENGR Engineering Final | Passed | ||
| 08/28/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 08/27/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 08/27/2025 | COT - HCBU - Building Progress | Passed | 8-27-25: approved. | |
| 08/27/2025 | COT - HCEL - Electrical Progress | Passed | 8-27-25: approved. | |
| 08/27/2025 | COT - HCME - Mechanical Progress | Passed | 8-27-25:,approved | |
| 08/27/2025 | COT - HCPL - Plumbing Progress | Passed | 8-27-25: approved | |
| 09/02/2025 | COT - FCON - Fire - Final | Passed | ||
| 09/02/2025 | COT - HCBU - Building Above Ceiling | Passed | 9-2-25: approved. | |
| 09/02/2025 | COT - HCEL - Electrical Above Ceiling | Passed | 9-2-25: approved. | |
| 09/02/2025 | COT - HCEL - Electrical Final | Passed | 9-2-25: electrical final approved. | |
| 09/02/2025 | COT - HCEL - Electrical Intermediate | Passed | 9-2-25: approved. | |
| 09/02/2025 | COT - HCME - Mechanical Above Ceiling | Passed | 9-2-25: approved. | |
| 09/02/2025 | COT - HCME - Mechanical Final | Passed | 9-2-25: mechanical final approved. | |
| 09/02/2025 | COT - HCME - Mechanical Intermediate | Passed | 9-2-25: approved. | |
| 09/02/2025 | COT - HCPL - Plumbing Above Ceiling | Passed | 9-2-25: approved. | |
| 09/02/2025 | COT - HCPL - Plumbing Final | Passed | 9-2-25: plumbing final approved. | |
| 09/02/2025 | COT - HCPL - Plumbing Intermediate | Passed | 9-2-25: approved. | |
| 09/09/2025 | COT - HCBU - Building Final | Passed | 9-9-25: Building Final Approved. Okay for Level 4 TCO-SEE PENDING CONDITIONS. |