Inspection Status: Re-inspection required
Inspection History: COT - HCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 05/19/2025 |
COT - HCPL - Plumbing Intermediate |
|
Re-inspection required |
5/19/25: (2)supports required at vertical runs at DVW, leak at test cap, (1) support required at domestic water at east bathroom in wall. Plumbing under test. |
| 08/27/2025 |
COT - HCPL - Plumbing Intermediate |
|
Re-inspection required |
8-27-25: pending conditions, required corrections to include: wrapping of hot piping on water heater, RFI for HVAC & RFI for receptacle relocation in office area, adjusting all interior /exit doors to open at 5 pounds of pressure, secure mc cable & fire foam penetration above electrical HV1 panel and at any horizontal penetration where piping/conduits extend through to another space. Existing electrical panels not in use must be "gutted" to the possible unlawful use at a later date and must be clearly labeled "panel not in use." |
| 09/02/2025 |
COT - HCPL - Plumbing Intermediate |
|
Passed |
9-2-25: approved. |