Permit: TC-COM-1024-02092
Permit Details
Apply Date:
10/31/2024
Applicant:
Katie Ledy
Description:
New warehouse with mezzinine
Permit Reviews
Permit Number - TC-COM-1024-02092
Permit Status: Approved
Permit Description: New warehouse with mezzinine
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/08/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/14/2026 | APPROVED |
| 10/31/2024 | COMMERCIAL REVIEW - FULL v.1 | 11/26/2024 | REQUIRES RESUBMIT |
| 07/02/2025 | RESTAMP - COMMERCIAL v.1 | 07/07/2025 | APPROVED |
| 01/03/2025 | COMMERCIAL REVIEW - FULL v.3 | 01/28/2025 | REQUIRES RESUBMIT |
| 12/06/2024 | COMMERCIAL REVIEW - FULL v.2 | 01/03/2025 | REQUIRES RESUBMIT |
| 09/12/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/22/2025 | APPROVED |
| 07/22/2026 | SPECIAL INSPECTION REVIEW v.2 | 07/23/2026 | REQUIRES RESUBMIT |
| 06/24/2025 | COMMERCIAL REVIEW - FULL v.4 | 07/02/2025 | APPROVED |
| 10/10/2025 | COMMERCIAL REVIEW - FULL REVISION v.2 | 10/15/2025 | APPROVED |
| 07/02/2026 | SPECIAL INSPECTION REVIEW v.1 | 07/07/2026 | REQUIRES RESUBMIT |
| 10/03/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 10/07/2025 | REQUIRES RESUBMIT |
| 08/10/2026 | SPECIAL INSPECTION REVIEW v.3 | 08/11/2026 | APPROVED |
Conditions
Permit Number - TC-COM-1024-02092
Permit Status: Approved
Permit Description: New warehouse with mezzinine
| Date | Description | Comments |
|---|---|---|
| 01/07/2025 | AIR BALANCING REPORT IS REQUIRED. | |
| 01/07/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 10/31/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 01/07/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 01/07/2025 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 01/07/2025 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 01/07/2025 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 01/07/2025 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
| 01/07/2025 | Post-Installed Anchor Inspection Report is required. | |
| 01/03/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 01/07/2025 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 10/31/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 01/07/2025 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Approved
Permit Number: TC-COM-1024-02092
Permite Description: New warehouse with mezzinine
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/19/2025 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | |
| 04/02/2026 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | partial for bottom floor |
| 11/13/2025 | COT - HCEL - Electrical Underground | N/A | Partial Pass | |
| 11/19/2025 | COT - HCEL - Grounding/Bonding | N/A | Partial Pass | |
| 07/16/2026 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 07/16/2026 | COT - HCPL - Gas Final | N/A | Not Applicable | |
| 07/16/2026 | COT - HCPL - Gas Pressure Test | N/A | Not Applicable |
Completed Inspections
Permit Status: Approved
Permit Number: TC-COM-1024-02092
Permit Description: New warehouse with mezzinine
Total Completed Inspections - 24