Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0824-01656
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
1151 E HERMANS RD BLDG 805
Address NEW:
1151 E HERMANS RD BLDG 805
Apply Date:
08/23/2024
Applicant:
Gary Wellborn
Description:
The interior scope of work entails interior tenant improvement of 18,625 SF of existing office to be converted to a laboratory use. The laboratory use is for testing and is not a chemical laboratory space with hazardous chemical storage. New laboratory will include testing chambers, small bridge cranes, and other owner supplied equipment. Exterior work includes installation of a LN2 tank, associated concrete pad, and a 780 SF canopy structure. The new canopy is an extension of the existing canopy and will be added at southeast corner of building.
Permit Reviews
Permit Number - TC-COM-0824-01656
Permit Status: Complete
Permit Description: The interior scope of work entails interior tenant improvement of 18,625 SF of existing office to be converted to a laboratory use. The laboratory use is for testing and is not a chemical laboratory space with hazardous chemical storage. New laboratory will include testing chambers, small bridge cranes, and other owner supplied equipment. Exterior work includes installation of a LN2 tank, associated concrete pad, and a 780 SF canopy structure. The new canopy is an extension of the existing canopy and will be added at southeast corner of building.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/03/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 07/03/2025 | REQUIRES RESUBMIT |
| 03/17/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/18/2025 | REQUIRES RESUBMIT |
| 08/27/2024 | COMMERCIAL REVIEW - FULL v.1 | 09/26/2024 | REQUIRES RESUBMIT |
| 11/18/2024 | RESTAMP - COMMERCIAL v.1 | 11/21/2024 | APPROVED |
| 10/16/2024 | COMMERCIAL REVIEW - FULL v.2 | 10/22/2024 | REQUIRES RESUBMIT |
| 11/08/2024 | COMMERCIAL REVIEW - FULL v.3 | 11/18/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0824-01656
Permit Status: Complete
Permit Description: The interior scope of work entails interior tenant improvement of 18,625 SF of existing office to be converted to a laboratory use. The laboratory use is for testing and is not a chemical laboratory space with hazardous chemical storage. New laboratory will include testing chambers, small bridge cranes, and other owner supplied equipment. Exterior work includes installation of a LN2 tank, associated concrete pad, and a 780 SF canopy structure. The new canopy is an extension of the existing canopy and will be added at southeast corner of building.
Total Outstanding Activity Conditions - 13
| Date | Name |
|---|---|
| 11/18/2024 | AIR BALANCING REPORT IS REQUIRED. |
| 11/18/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 11/18/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 11/18/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 11/18/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 11/18/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 11/18/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 11/18/2024 | Masonry Inspection Report submittal review is required. |
| 11/18/2024 | Post-Installed Anchor Inspection Report is required. |
| 11/18/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
| 11/18/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 11/18/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 11/18/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Conditions
Permit Number - TC-COM-0824-01656
Permit Status: Complete
Permit Description: The interior scope of work entails interior tenant improvement of 18,625 SF of existing office to be converted to a laboratory use. The laboratory use is for testing and is not a chemical laboratory space with hazardous chemical storage. New laboratory will include testing chambers, small bridge cranes, and other owner supplied equipment. Exterior work includes installation of a LN2 tank, associated concrete pad, and a 780 SF canopy structure. The new canopy is an extension of the existing canopy and will be added at southeast corner of building.
| Date | Description | Comments |
|---|---|---|
| 08/27/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 11/19/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0824-01656
Permite Description: The interior scope of work entails interior tenant improvement of 18,625 SF of existing office to be converted to a laboratory use. The laboratory use is for testing and is not a chemical laboratory space with hazardous chemical storage. New laboratory will include testing chambers, small bridge cranes, and other owner supplied equipment. Exterior work includes installation of a LN2 tank, associated concrete pad, and a 780 SF canopy structure. The new canopy is an extension of the existing canopy and will be added at southeast corner of building.
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/29/2024 | COT - HCBU - Framing | N/A | Partial Pass | 11/29/24: framing per plan at perimeter walls at rooms 101,102,112,107,106. Pending east walls. Ok to insulate and drywall. |
| 03/11/2025 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 3/11/25: partial pass for infill at masonry wall ok to proceed. |
| 07/24/2025 | COT - HCPL - Gas Final | N/A | Not Applicable | |
| 03/27/2025 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 1/21/25: electrical intermediate/ progress in Area A ( rough-in of all conduits/ gutter and trays) ok to proceed. Grounding of trays approved. 2/28/25: electrical intermediate / progress in Area C (rough-in of all conduits/ gutter and trays), grounding per plan ok to proceed. 3/27/25: transformers wired per plan ok to proceed, |
| 07/24/2025 | COT - HCPL - Gas Pressure Test | N/A | Not Applicable | |
| 05/01/2025 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 5/1/25: reinforcement per plan at Bridge crane footings (4) in Area B and (4) in Area D. Ok to proceed with concrete placement. |
| 05/01/2025 | COT - HCBU - Preslab | N/A | Partial Pass | 5/1/25: reinforcement per plan at Bridge crane footings (4) in Area B and (4) in Area D. Ok to proceed with concrete placement. |
| 02/28/2025 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 2/28/25: chilled water supply and return per plan at Area A and C |
| 02/28/2025 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 1/21/25: Hard duct installed per plans in Area A, seal all connections with duct sealer, diffusers installed per plan. Ok to proceed. 2/28/25: Hard duct installed per plans in Area C, ok to proceed. |
| COT - FCON - Sprinkler - Final | N/A | Not Ready | ||
| COT - FCON - Alarm - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0824-01656
Permit Description: The interior scope of work entails interior tenant improvement of 18,625 SF of existing office to be converted to a laboratory use. The laboratory use is for testing and is not a chemical laboratory space with hazardous chemical storage. New laboratory will include testing chambers, small bridge cranes, and other owner supplied equipment. Exterior work includes installation of a LN2 tank, associated concrete pad, and a 780 SF canopy structure. The new canopy is an extension of the existing canopy and will be added at southeast corner of building.
Total Completed Inspections - 20