Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
08/23/2024
Applicant:
Gary Wellborn
Description:
The interior scope of work entails interior tenant improvement of 18,625 SF of existing office to be converted to a laboratory use. The laboratory use is for testing and is not a chemical laboratory space with hazardous chemical storage. New laboratory will include testing chambers, small bridge cranes, and other owner supplied equipment. Exterior work includes installation of a LN2 tank, associated concrete pad, and a 780 SF canopy structure. The new canopy is an extension of the existing canopy and will be added at southeast corner of building.

Permit Reviews

Permit Number - TC-COM-0824-01656
Permit Status: Complete
Permit Description: The interior scope of work entails interior tenant improvement of 18,625 SF of existing office to be converted to a laboratory use. The laboratory use is for testing and is not a chemical laboratory space with hazardous chemical storage. New laboratory will include testing chambers, small bridge cranes, and other owner supplied equipment. Exterior work includes installation of a LN2 tank, associated concrete pad, and a 780 SF canopy structure. The new canopy is an extension of the existing canopy and will be added at southeast corner of building.
Start Date Submittal Complete Date Status  
07/03/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 07/03/2025 REQUIRES RESUBMIT Review Details
03/17/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/18/2025 REQUIRES RESUBMIT Review Details
08/27/2024 COMMERCIAL REVIEW - FULL v.1 09/26/2024 REQUIRES RESUBMIT Review Details
11/18/2024 RESTAMP - COMMERCIAL v.1 11/21/2024 APPROVED Review Details
10/16/2024 COMMERCIAL REVIEW - FULL v.2 10/22/2024 REQUIRES RESUBMIT Review Details
11/08/2024 COMMERCIAL REVIEW - FULL v.3 11/18/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0824-01656
Permit Status: Complete
Permit Description: The interior scope of work entails interior tenant improvement of 18,625 SF of existing office to be converted to a laboratory use. The laboratory use is for testing and is not a chemical laboratory space with hazardous chemical storage. New laboratory will include testing chambers, small bridge cranes, and other owner supplied equipment. Exterior work includes installation of a LN2 tank, associated concrete pad, and a 780 SF canopy structure. The new canopy is an extension of the existing canopy and will be added at southeast corner of building.
Total Outstanding Activity Conditions - 13
Date Name
11/18/2024 AIR BALANCING REPORT IS REQUIRED.
11/18/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
11/18/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
11/18/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
11/18/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
11/18/2024 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
11/18/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
11/18/2024 Masonry Inspection Report submittal review is required.
11/18/2024 Post-Installed Anchor Inspection Report is required.
11/18/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
11/18/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
11/18/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
11/18/2024 WATER STERILIZATION REPORT IS REQUIRED.

Conditions

Permit Number - TC-COM-0824-01656
Permit Status: Complete
Permit Description: The interior scope of work entails interior tenant improvement of 18,625 SF of existing office to be converted to a laboratory use. The laboratory use is for testing and is not a chemical laboratory space with hazardous chemical storage. New laboratory will include testing chambers, small bridge cranes, and other owner supplied equipment. Exterior work includes installation of a LN2 tank, associated concrete pad, and a 780 SF canopy structure. The new canopy is an extension of the existing canopy and will be added at southeast corner of building.
Date Description Comments
08/27/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
11/19/2024 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0824-01656
Permite Description: The interior scope of work entails interior tenant improvement of 18,625 SF of existing office to be converted to a laboratory use. The laboratory use is for testing and is not a chemical laboratory space with hazardous chemical storage. New laboratory will include testing chambers, small bridge cranes, and other owner supplied equipment. Exterior work includes installation of a LN2 tank, associated concrete pad, and a 780 SF canopy structure. The new canopy is an extension of the existing canopy and will be added at southeast corner of building.
Total Outstanding Inspections - 11
Last Inspection Date Description Inspector Results Comments
11/29/2024 COT - HCBU - Framing N/A Partial Pass 11/29/24: framing per plan at perimeter walls at rooms 101,102,112,107,106. Pending east walls. Ok to insulate and drywall.
03/11/2025 COT - HCBU - Masonry Pregrout N/A Partial Pass 3/11/25: partial pass for infill at masonry wall ok to proceed.
07/24/2025 COT - HCPL - Gas Final N/A Not Applicable
03/27/2025 COT - HCEL - Electrical Intermediate N/A Partial Pass 1/21/25: electrical intermediate/ progress in Area A ( rough-in of all conduits/ gutter and trays) ok to proceed. Grounding of trays approved.
2/28/25: electrical intermediate / progress in Area C (rough-in of all conduits/ gutter and trays), grounding per plan ok to proceed.
3/27/25: transformers wired per plan ok to proceed,
07/24/2025 COT - HCPL - Gas Pressure Test N/A Not Applicable
05/01/2025 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass 5/1/25: reinforcement per plan at Bridge crane footings (4) in Area B and (4) in Area D. Ok to proceed with concrete placement.
05/01/2025 COT - HCBU - Preslab N/A Partial Pass 5/1/25: reinforcement per plan at Bridge crane footings (4) in Area B and (4) in Area D. Ok to proceed with concrete placement.
02/28/2025 COT - HCPL - Plumbing Intermediate N/A Partial Pass 2/28/25: chilled water supply and return per plan at Area A and C
02/28/2025 COT - HCME - Mechanical Intermediate N/A Partial Pass 1/21/25: Hard duct installed per plans in Area A, seal all connections with duct sealer, diffusers installed per plan. Ok to proceed.
2/28/25: Hard duct installed per plans in Area C, ok to proceed.
COT - FCON - Sprinkler - Final N/A Not Ready
COT - FCON - Alarm - Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0824-01656
Permit Description: The interior scope of work entails interior tenant improvement of 18,625 SF of existing office to be converted to a laboratory use. The laboratory use is for testing and is not a chemical laboratory space with hazardous chemical storage. New laboratory will include testing chambers, small bridge cranes, and other owner supplied equipment. Exterior work includes installation of a LN2 tank, associated concrete pad, and a 780 SF canopy structure. The new canopy is an extension of the existing canopy and will be added at southeast corner of building.
Total Completed Inspections - 20
Date Description Inspector Results Comments
03/27/2025 COT - HCBU - Framing Passed
03/27/2025 COT - HCBU - Masonry Pregrout Passed
07/24/2025 COT - HCPL - Plumbing Above Ceiling Passed
07/24/2025 COT - HCBU - Building Above Ceiling Passed
07/24/2025 COT - HCME - Mechanical Final Passed
07/24/2025 COT - HCEL - Electrical Intermediate Passed
07/24/2025 COT - HCEL - Electrical Above Ceiling Passed
07/24/2025 TRSP - ROW - Final/Close-Out Passed
07/24/2025 ENGR Engineering Final Passed Bollards installed per plan, spacing and hgt is correct.
07/24/2025 COT - HCBU - Excavation/Rebar/Zoning Passed
07/24/2025 COT - HCBU - Preslab Passed
07/24/2025 COT - HCPL - Plumbing Final Passed
07/24/2025 COT - HCPL - Plumbing Intermediate Passed
07/24/2025 COT - HCEL - Electrical Final Passed
07/24/2025 COT - HCME - Mechanical Intermediate Passed
07/24/2025 COT - HCME - Mechanical Above Ceiling Passed
08/22/2025 COT - FCON - Sprinkler - Final Passed
08/25/2025 COT - HCBU - Building Final Passed
11/14/2025 COT - FCON - Alarm - Final Passed
11/14/2025 COT - FCON - Fire - Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-FAC24111 AND FAC24134 BLDG 805 HARDWARE LAB DESIGN DRAWINGS (SEALED 100 DRAWINGS)- RESUBMITTAL 11-07-2024_V3.PDF DOCUMENTS VIEW
FAC24111 AND FAC24134 BLDG 805 HARDWARE LAB DESIGN DRAWINGS -SEALED STRUCTURAL CALCS REV 1_V2.PDF DOCUMENTS VIEW
IECC - INTERIOR LIGHTING COMPLIANCE REPORT (RAYTHEON BLDG 805 LAB)_V1.PDF DOCUMENTS VIEW
IECC - MECHANICAL COMPLIANCE REPORT - COMCHECK (RAYTHEON BLDG 805 LAB)_V1.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT - WESTERN TECH - MT SIGNED-2024-10-11_V1.PDF DOCUMENTS VIEW