Inspection Status: Partial Pass

Inspection History: COT - HCME - Mechanical Intermediate

Date Description Inspector Results Comments
01/21/2025 COT - HCME - Mechanical Intermediate Partial Pass 1/21/25: Hard duct installed per plans in Area A, seal all connections with duct sealer, diffusers installed per plan. Ok to proceed.
02/28/2025 COT - HCME - Mechanical Intermediate Partial Pass 1/21/25: Hard duct installed per plans in Area A, seal all connections with duct sealer, diffusers installed per plan. Ok to proceed.
2/28/25: Hard duct installed per plans in Area C, ok to proceed.
04/24/2025 COT - HCME - Mechanical Intermediate Partial Pass 1/21/25: Hard duct installed per plans in Area A, seal all connections with duct sealer, diffusers installed per plan. Ok to proceed.
2/28/25: Hard duct installed per plans in Area C, ok to proceed.
4/24/25: Hard duct installed per plan in Area D, ok to proceed. mechanical progress for hard duct in area B
07/24/2025 COT - HCME - Mechanical Intermediate Passed