Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
Permit Number - TC-COM-0824-01656
Inspection Description - COT - HCBU - Excavation/Rebar/Zoning
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/01/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 5/1/25: reinforcement per plan at Bridge crane footings (4) in Area B and (4) in Area D. Ok to proceed with concrete placement. | |
| 05/12/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 5/1/25: reinforcement per plan at Bridge crane footings (4) in Area B and (4) in Area D. Ok to proceed with concrete placement. 5/1/25: reinforcement per plan at Bridge crane footings (4) in Area B and (4) in Area D. Ok to proceed with concrete placement. 5/12/25: reinforcement per plan at Tank Structure foundation (#6 12" o.c E.W T&B), House keep pad reinforced per plans ok to proceed. |
|
| 05/15/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 05/23/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 5-23-25, reinforcement for 13x13x3' deep motion table isolation pad in rm. 106 at Building 805 together with vib.shaker table foundation pad in rm. 109 at 6x 10x 1' deep verified as per approved plans-Okay to pour concrete. (3rd. Party-Western Tech inspector approved inspection). | |
| 05/23/2025 | COT - HCBU - Excavation/Rebar/Zoning | Re-inspection required | 5-23-25, called point of contact at 1127 hours but received no answer. Arrived on site at approximately 1131 hours-waited 10 minutes and left. | |
| 07/24/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed |