Inspection Status: Partial Pass

Inspection History: COT - HCBU - Preslab  

Date Description Inspector Results Comments
05/01/2025 COT - HCBU - Preslab   Partial Pass 5/1/25: reinforcement per plan at Bridge crane footings (4) in Area B and (4) in Area D. Ok to proceed with concrete placement.
05/12/2025 COT - HCBU - Preslab   Partial Pass 5/1/25: reinforcement per plan at Bridge crane footings (4) in Area B and (4) in Area D. Ok to proceed with concrete placement.
5/12/25: reinforcement per plan at Tank Structure foundation (#6 12" o.c E.W T&B), House keep pad reinforced per plans ok to proceed.
07/24/2025 COT - HCBU - Preslab   Passed