Permit: TC-COM-0625-01274
Permit Details
Apply Date:
06/30/2025
Applicant:
Eloy Stevens
Description:
addition - shell building for hotel lobby
Permit Reviews
Permit Number - TC-COM-0625-01274
Permit Status: Inspections
Permit Description: addition - shell building for hotel lobby
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/30/2025 | COMMERCIAL REVIEW - FULL v.4 | 11/13/2025 | APPROVED |
| 11/19/2025 | ADMINISTRATIVE v.2 | 11/19/2025 | APPROVED |
| 10/29/2025 | COMMERCIAL REVIEW - FULL v.3 | 10/29/2025 | REQUIRES RESUBMIT |
| 11/17/2025 | ADMINISTRATIVE v.1 | 11/17/2025 | REQUIRES RESUBMIT |
| 11/26/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 11/28/2025 | APPROVED |
| 11/19/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/21/2025 | REQUIRES RESUBMIT |
| 09/29/2025 | COMMERCIAL REVIEW - FULL v.2 | 10/28/2025 | REQUIRES RESUBMIT |
| 11/13/2025 | RESTAMP - COMMERCIAL v.1 | 11/17/2025 | APPROVED |
| 07/03/2025 | COMMERCIAL REVIEW - FULL v.1 | 07/28/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0625-01274
Permit Status: Inspections
Permit Description: addition - shell building for hotel lobby
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 11/06/2025 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 11/06/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 11/06/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 11/06/2025 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 11/06/2025 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
| 11/06/2025 | Masonry Inspection Report submittal review is required. |
| 11/06/2025 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Conditions
Permit Number - TC-COM-0625-01274
Permit Status: Inspections
Permit Description: addition - shell building for hotel lobby
| Date | Description | Comments |
|---|---|---|
| 07/03/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 07/03/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 11/06/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0625-01274
Permite Description: addition - shell building for hotel lobby
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/04/2026 | COT - HCBU - Preslab | N/A | Partial Pass | Partial pass. Footings per F schedules. From Grid lines D9. 1-5. Two Interior columns footers included. Four columns north of building on grid line B1-A. F-C pending west pop out. Elevator pit approved per reinforcement plan. Okay for concrete placement at all progress areas. 5/4/2026 |
| 07/31/2026 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 7-31-26: excavation/reinforcement 4-footings 1 on on west side and 3 on east side Adjacent and north of elevator shaft verified per footing schedule/details. Okay for concrete placement. |
| 09/02/2026 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | |
| 09/22/2026 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 9/22/2026 Partial pass. 3rd lift approved at all walls. Note: Lintel areas at door way kitchen area and west outdoor patio Lintel above okay to proceed up to 6’ due to continuous solid grout above those areas. Okay to grout all progress areas. |
| 09/23/2026 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 9/23/2026 Partial pass. Electrical underground. Secondaries. Total of x6 4” schedule 40 conduit at a depth of 48” in place from transformer ran to new CT can and other electrical equipment rear of kitchen wall. Okay to backfill all progress areas. Ensure caution tape is in place after first lift of compaction. |