Inspection Status: Partial Pass
Inspection History: COT - HCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 05/04/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
Partial pass. Footings per F schedules. From Grid lines D9. 1-5. Two Interior columns footers included. Four columns north of building on grid line B1-A. F-C pending west pop out. Elevator pit approved per reinforcement plan. Okay for concrete placement at all progress areas. 5/4/2026 |