Inspection Status: Re-inspection required
Inspection History: COT - HCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 06/10/2026 |
COT - HCBU - Masonry Pregrout |
|
Re-inspection required |
6-10-26: not ready-missing vertical reinforcement. Reschedule at your convenience. |
| 06/11/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
6-11-26: reinforcement verified at elevator shaft walls-okay to grout 1st lift at 4'. |
| 06/18/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
|
| 06/25/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
|
| 07/08/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Perimeter walls 2nd lift approved. 7/8/2026 |
| 08/05/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
8/5/2026 Partial pass. Stem wall south east end. Bond beam at east end center wall. Single Pillar at north east side, stem wall at west end near door entry approved. Okay to grout all progress areas. |
| 08/11/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
8/11/2026 Partial pass. 1st lift at 4’ east end wall up to center L wall. West end wall of building for storage 1st lift at 4’ okay to grout all progress areas. |
| 08/14/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
8/14/2026 partial pass. 2nd lift at 8' all walls approved. Okay to grout progress areas. |