Inspection Status: Not Ready
Inspection History: COT - HCEL - Electrical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 09/16/2026 |
COT - HCEL - Electrical Progress |
|
Not Ready |
9/16/2026 Inspection at time is for electrical underground. Not ready. Trench is too shallow. Ensure conduit is measured to top of pipe no less than 3'. |
| 09/23/2026 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
9/23/2026 Partial pass. Electrical underground. Secondaries. Total of x6 4” schedule 40 conduit at a depth of 48” in place from transformer ran to new CT can and other electrical equipment rear of kitchen wall. Okay to backfill all progress areas. Ensure caution tape is in place after first lift of compaction. |