Permit: TC-COM-0526-00737
Permit Details
Status:
Fees Paid
Type:
Commercial Building
Address:
8755 S RITA RD BLDG 2
Address NEW:
8755 S RITA RD BLDG 2
Apply Date:
05/19/2026
Applicant:
Charlie Smith
Description:
Wastewater pretreatment expansion: 1. New concrete slab with canopy (sides are open air) covers wastewater process equipment. 2. New pre-engineered metal building to house electrical equipment, blowers, chemical dosing equipment. 3. Two new bolted-steel, open-top, above grade tanks wastewater equalization and biological treatment, two new closed-top FRP sludge storage tanks. 4. New cooling tower on 12’x12’ concrete slab. Split Commercial New Building application into (2) permits: 1. (******THIS PERMIT******): “Permit #1” two bolted steel wastewater treatment tanks, cooling tower, sludge storage tanks, underground piping. Structural foundation/slab design. Special Inspections Certificate form be submitted prior to Start of Inspections as deferred submittal. 2. SEE SEPARATE PERMIT: Permit #2 broken into “Phase 1” foundation/slab design to expedite review of concrete work. Permit #2 Phase 2 above-grade building/canopy structure, equipment anchorage, electrical, heating/cooling, plumbing disciplines.
Permit Reviews
Permit Number - TC-COM-0526-00737
Permit Status: Fees paid
Permit Description: Wastewater pretreatment expansion:
1. New concrete slab with canopy (sides are open air) covers wastewater process equipment. 2. New pre-engineered metal building to house electrical equipment, blowers, chemical dosing equipment. 3. Two new bolted-steel, open-top, above grade tanks wastewater equalization and biological treatment, two new closed-top FRP sludge storage tanks. 4. New cooling tower on 12’x12’ concrete slab.
Split Commercial New Building application into (2) permits:
1. (******THIS PERMIT******): “Permit #1” two bolted steel wastewater treatment tanks, cooling tower, sludge storage tanks, underground piping. Structural foundation/slab design. Special Inspections Certificate form be submitted prior to Start of Inspections as deferred submittal.
2. SEE SEPARATE PERMIT: Permit #2 broken into “Phase 1” foundation/slab design to expedite review of concrete work. Permit #2 Phase 2 above-grade building/canopy structure, equipment anchorage, electrical, heating/cooling, plumbing disciplines.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/16/2026 | COMMERCIAL REVIEW - FULL v.2 | 07/08/2026 | REQUIRES RESUBMIT |
| 07/20/2026 | COMMERCIAL REVIEW - FULL v.3 | N/A | IN REVIEW |
| 05/20/2026 | COMMERCIAL REVIEW - FULL v.1 | 06/10/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0526-00737
Permit Status: Fees paid
Permit Description: Wastewater pretreatment expansion:
1. New concrete slab with canopy (sides are open air) covers wastewater process equipment. 2. New pre-engineered metal building to house electrical equipment, blowers, chemical dosing equipment. 3. Two new bolted-steel, open-top, above grade tanks wastewater equalization and biological treatment, two new closed-top FRP sludge storage tanks. 4. New cooling tower on 12’x12’ concrete slab.
Split Commercial New Building application into (2) permits:
1. (******THIS PERMIT******): “Permit #1” two bolted steel wastewater treatment tanks, cooling tower, sludge storage tanks, underground piping. Structural foundation/slab design. Special Inspections Certificate form be submitted prior to Start of Inspections as deferred submittal.
2. SEE SEPARATE PERMIT: Permit #2 broken into “Phase 1” foundation/slab design to expedite review of concrete work. Permit #2 Phase 2 above-grade building/canopy structure, equipment anchorage, electrical, heating/cooling, plumbing disciplines.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 05/20/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
| 06/03/2026 | SPECIAL INSPECTION FOR REINFORCING STEEL IS REQUIRED. |
| 06/04/2026 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 06/04/2026 | SPECIAL INSPECTION FOR POST INSTALLED/EPOXY ANCHORS IS REQUIRED. |
| 06/04/2026 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 06/05/2026 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Conditions
Permit Number - TC-COM-0526-00737
Permit Status: Fees paid
Permit Description: Wastewater pretreatment expansion:
1. New concrete slab with canopy (sides are open air) covers wastewater process equipment. 2. New pre-engineered metal building to house electrical equipment, blowers, chemical dosing equipment. 3. Two new bolted-steel, open-top, above grade tanks wastewater equalization and biological treatment, two new closed-top FRP sludge storage tanks. 4. New cooling tower on 12’x12’ concrete slab.
Split Commercial New Building application into (2) permits:
1. (******THIS PERMIT******): “Permit #1” two bolted steel wastewater treatment tanks, cooling tower, sludge storage tanks, underground piping. Structural foundation/slab design. Special Inspections Certificate form be submitted prior to Start of Inspections as deferred submittal.
2. SEE SEPARATE PERMIT: Permit #2 broken into “Phase 1” foundation/slab design to expedite review of concrete work. Permit #2 Phase 2 above-grade building/canopy structure, equipment anchorage, electrical, heating/cooling, plumbing disciplines.
| Date | Description | Comments |
|---|---|---|
| 05/20/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 06/26/2026 | No electrical or outdoor lighting to be installed during this phase. All electrical and outdoor lighting to be installed and inspected during the phase 2 submittal 2, which is in reference to the construction of the shade canopy and conditioned space buildings. |