Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Fees Paid
Type:
Commercial Building
Address NEW:
8755 S RITA RD BLDG 2
Apply Date:
05/19/2026
Applicant:
Charlie Smith
Description:
Wastewater pretreatment expansion: 1. New concrete slab with canopy (sides are open air) covers wastewater process equipment. 2. New pre-engineered metal building to house electrical equipment, blowers, chemical dosing equipment. 3. Two new bolted-steel, open-top, above grade tanks wastewater equalization and biological treatment, two new closed-top FRP sludge storage tanks. 4. New cooling tower on 12’x12’ concrete slab. Split Commercial New Building application into (2) permits: 1. (******THIS PERMIT******): “Permit #1” two bolted steel wastewater treatment tanks, cooling tower, sludge storage tanks, underground piping. Structural foundation/slab design. Special Inspections Certificate form be submitted prior to Start of Inspections as deferred submittal. 2. SEE SEPARATE PERMIT: Permit #2 broken into “Phase 1” foundation/slab design to expedite review of concrete work. Permit #2 Phase 2 above-grade building/canopy structure, equipment anchorage, electrical, heating/cooling, plumbing disciplines.

Permit Reviews

Permit Number - TC-COM-0526-00737
Permit Status: Fees paid
Permit Description: Wastewater pretreatment expansion: 1. New concrete slab with canopy (sides are open air) covers wastewater process equipment. 2. New pre-engineered metal building to house electrical equipment, blowers, chemical dosing equipment. 3. Two new bolted-steel, open-top, above grade tanks wastewater equalization and biological treatment, two new closed-top FRP sludge storage tanks. 4. New cooling tower on 12’x12’ concrete slab. Split Commercial New Building application into (2) permits: 1. (******THIS PERMIT******): “Permit #1” two bolted steel wastewater treatment tanks, cooling tower, sludge storage tanks, underground piping. Structural foundation/slab design. Special Inspections Certificate form be submitted prior to Start of Inspections as deferred submittal. 2. SEE SEPARATE PERMIT: Permit #2 broken into “Phase 1” foundation/slab design to expedite review of concrete work. Permit #2 Phase 2 above-grade building/canopy structure, equipment anchorage, electrical, heating/cooling, plumbing disciplines.
Start Date Submittal Complete Date Status  
06/16/2026 COMMERCIAL REVIEW - FULL v.2 07/08/2026 REQUIRES RESUBMIT Review Details
07/20/2026 COMMERCIAL REVIEW - FULL v.3 N/A IN REVIEW Review Details
05/20/2026 COMMERCIAL REVIEW - FULL v.1 06/10/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0526-00737
Permit Status: Fees paid
Permit Description: Wastewater pretreatment expansion: 1. New concrete slab with canopy (sides are open air) covers wastewater process equipment. 2. New pre-engineered metal building to house electrical equipment, blowers, chemical dosing equipment. 3. Two new bolted-steel, open-top, above grade tanks wastewater equalization and biological treatment, two new closed-top FRP sludge storage tanks. 4. New cooling tower on 12’x12’ concrete slab. Split Commercial New Building application into (2) permits: 1. (******THIS PERMIT******): “Permit #1” two bolted steel wastewater treatment tanks, cooling tower, sludge storage tanks, underground piping. Structural foundation/slab design. Special Inspections Certificate form be submitted prior to Start of Inspections as deferred submittal. 2. SEE SEPARATE PERMIT: Permit #2 broken into “Phase 1” foundation/slab design to expedite review of concrete work. Permit #2 Phase 2 above-grade building/canopy structure, equipment anchorage, electrical, heating/cooling, plumbing disciplines.
Total Outstanding Activity Conditions - 6
Date Name
05/20/2026 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
06/03/2026 SPECIAL INSPECTION FOR REINFORCING STEEL IS REQUIRED.
06/04/2026 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
06/04/2026 SPECIAL INSPECTION FOR POST INSTALLED/EPOXY ANCHORS IS REQUIRED.
06/04/2026 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
06/05/2026 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Conditions

Permit Number - TC-COM-0526-00737
Permit Status: Fees paid
Permit Description: Wastewater pretreatment expansion: 1. New concrete slab with canopy (sides are open air) covers wastewater process equipment. 2. New pre-engineered metal building to house electrical equipment, blowers, chemical dosing equipment. 3. Two new bolted-steel, open-top, above grade tanks wastewater equalization and biological treatment, two new closed-top FRP sludge storage tanks. 4. New cooling tower on 12’x12’ concrete slab. Split Commercial New Building application into (2) permits: 1. (******THIS PERMIT******): “Permit #1” two bolted steel wastewater treatment tanks, cooling tower, sludge storage tanks, underground piping. Structural foundation/slab design. Special Inspections Certificate form be submitted prior to Start of Inspections as deferred submittal. 2. SEE SEPARATE PERMIT: Permit #2 broken into “Phase 1” foundation/slab design to expedite review of concrete work. Permit #2 Phase 2 above-grade building/canopy structure, equipment anchorage, electrical, heating/cooling, plumbing disciplines.
Date Description Comments
05/20/2026 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
06/26/2026 No electrical or outdoor lighting to be installed during this phase. All electrical and outdoor lighting to be installed and inspected during the phase 2 submittal 2, which is in reference to the construction of the shade canopy and conditioned space buildings.