Permit Number: TC-COM-0526-00737
Parcel: 14122004L

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.2

Permit Number - TC-COM-0526-00737
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
07/07/2026 Restamp Commercial Building APPROVED
07/08/2026 Restamp Site Engineering APPROVED
07/06/2026 Site Zoning Standard APPROVED Associated DPs (TD-DEV-0126-00008 and TD-DEV-0326-00077) have been approved.
06/26/2026 Commercial Electrical Standard NOT REQUIRED No electrical or outdoor lighting to be installed during this phase. All electrical and outdoor lighting to be installed and inspected during the phase 2 submittal 2, which is in reference to the construction of the shade canopy and conditioned space buildings.
06/26/2026 Outdoor Lighting Standard NOT REQUIRED No electrical or outdoor lighting to be installed during this phase. All electrical and outdoor lighting to be installed and inspected during the phase 2 submittal 2, which is in reference to the construction of the shade canopy and conditioned space buildings.
07/08/2026 Bldg Permits - Post Review Express PENDING ASSIGNMENT
07/08/2026 Restamp Commercial Plumbing REQUIRES RESUBMIT 1. Show how the existing 8 inch sewer will be protected when the foundations for the canopy and the conditioned building are constructed over the sewer pipe. Reference: Section 305.1, IPC 2024.
2. Provide the drawings showing the construction of the process and plumbing piping that will be installed as part of the scope of work for permit #1. Reference: Section 107.2.1, IBC 2024.

These comments have been made due to the changing scope of work for permit #1. If you have any questions about this review comment, I can be reached at Robert.Sherry@tucsonaz.gov.
06/16/2026 PDSD Application Completeness Express REVIEW COMPLETED
07/07/2026 Restamp Fire New Construction REVIEW COMPLETED