Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
05/12/2025
Applicant:
Ed Turpin
Description:
New pre-engineered metal shop building for TEP at their Irvington Campus.

Permit Reviews

Permit Number - TC-COM-0525-00974
Permit Status: Complete
Permit Description: New pre-engineered metal shop building for TEP at their Irvington Campus.
Start Date Submittal Complete Date Status  
12/12/2025 COMMERCIAL REVIEW - FULL REVISION v.1 01/14/2026 APPROVED Review Details
05/15/2025 COMMERCIAL REVIEW - FULL v.1 06/13/2025 APPROVED Review Details
08/12/2025 RESTAMP - COMMERCIAL v.1 08/14/2025 APPROVED Review Details
06/20/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/24/2025 APPROVED Review Details
05/18/2026 SPECIAL INSPECTION REVIEW v.1 05/21/2026 APPROVED Review Details
05/07/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/11/2026 APPROVED Review Details
09/16/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/17/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-0525-00974
Permit Status: Complete
Permit Description: New pre-engineered metal shop building for TEP at their Irvington Campus.
Date Description Comments
05/15/2025 Building 53 needs to be added to Address on Construction Plans
06/05/2025 AIR BALANCING REPORT IS REQUIRED.
06/04/2025 Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents.
06/03/2025 SPECIAL INSPECTION OF CONCRETE IS REQUIRED. (PLACEMENT OF CAST-IN-PLACE ANCHOR BOLTS, REINFORCING STEEL AND PRESTRESSING TENDON PLACEMENT)
05/15/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
06/03/2025 SPECIAL INSPECTION OF POST-INSTALLED ANCHORS IS REQUIRED.
06/03/2025 PRE-ENGINEERED METAL BUILDING MUST BE SUBMITTED AND APPROVED PRIOR TO FINAL INSPECTIONS
05/15/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
06/05/2025 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0525-00974
Permite Description: New pre-engineered metal shop building for TEP at their Irvington Campus.
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
01/05/2026 COT - LCEL - Electrical Underground N/A Partial Pass 1-5-26: verified schedule 40 electrical conduits for panels and stub outs of pad at the east/west sides of site. Conduits range from 3/4" to 2 1/4"- okay to backfill progress areas.
01/05/2026 COT - LCEL - Grounding/Bonding N/A Partial Pass 1-6-26: Partial pass for UFER 3/0 copper. Will check water bonding at intermediates.
02/09/2026 BULD - Electrical Clearance N/A Not Ready Contractor cancelled, will reschedule for 10 February
05/08/2026 COT - BULD - SWG Clearance N/A Not Applicable 5-8-26: not applicable.
01/05/2026 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass 1-5-26: reinforcement for footings,column F4, and #5 hairpins around anchor zones verified per schedules located at S2.0& detail's 101-105-S3.0. Okay for concrete placement for slab at grade and at progress areas mentioned above. UFER 3/0 verified and located at north side of site.
05/08/2026 COT - LCBU - Stem Wall/Retaining Wall N/A Not Applicable 5-8-26: not applicable.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0525-00974
Permit Description: New pre-engineered metal shop building for TEP at their Irvington Campus.
Total Completed Inspections - 20
Date Description Inspector Results Comments
12/05/2025 COT - LCPL - Rough Soil Passed 12-5-25: underground plumbing verified under test & per plans. Okay to backfill with shading materials.
01/13/2026 COT - LCEL - Electrical Underground Passed Exterior conduits 1 1/4” and 1 1/2”. Ok to cover progress areas
03/20/2026 COT - LCBU - Framing Passed
03/20/2026 COT - LCEL - Electrical Intermediate Passed
03/20/2026 COT - LCPL - Plumbing Intermediate Passed
04/17/2026 COT - LCME - Mechanical Intermediate Passed 4-17-26: mechanical intermediates approved.
04/17/2026 COT - LCPL - Yard Water Line Passed 4-17-26: main water line approved. Okay to backfill using shading materials.
05/04/2026 COT - LCEL - Grounding/Bonding Passed 5-4-26: grounding/bonding approved.
05/08/2026 COT - LCBU - Excavation/Rebar/Zoning Passed 5-8-26: previously inspected & approved.
05/08/2026 ENGR Engineering Final Passed Building exterior is complete in accordance with approved plans. This does not encompass the accompanying Development Package.
05/08/2026 TRSP - ROW - Final/Close-Out Passed work had no impact to right of way, no damage, debris, or traffic control devices within right of way easement, approved
05/08/2026 COT - LCBU - Preslab Passed 5-8-26: previously inspected & approved.
05/08/2026 COT - LCEL - Electrical Above Ceiling Passed 5-8-26: approved.
05/08/2026 COT - LCEL - Outdoor Lighting Passed 5-8-26: approved.
05/08/2026 COT - LCBU - Roof Nailing Passed 5-8-26: approved.
06/02/2026 COT - LCEL - Electrical Final Passed 6-2-26: electrical final approved.
06/02/2026 COT - LCME - Mechanical Final Passed 6-2-26: mechanical final approved.
06/02/2026 COT - LCPL - Plumbing Final Passed 6-2-26: plumbing final approved.
07/10/2026 COT - FCON - Fire - Final Passed
07/10/2026 COT - LCBU - Building Final Passed