Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 01/05/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
1-5-26: reinforcement for footings,column F4, and #5 hairpins around anchor zones verified per schedules located at S2.0& detail's 101-105-S3.0. Okay for concrete placement for slab at grade and at progress areas mentioned above. UFER 3/0 verified and located at north side of site. |
| 02/11/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Canceled |
2-11-26: canceled by contractor. |
| 02/12/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2-12-26: excavation/reinforcements at electrical/equipment pad & turndown footings/pad for metal building verified per plans. Okay for concrete placement. |
| 05/08/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Passed |
5-8-26: previously inspected & approved. |
| 12/16/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
12-16-25: reinforcement/excavation on 14 exterior footers verified per S2.0 details F1/F2. There were 8 -F2 & 6-F1 footers with each having 4-#4 hooked dowels. Okay for concrete placement at progress areas. |
| 12/17/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
12-17-25: reinforcement/excavation on 10-F3 footers verified per S2.0-footing schedule. Okay for concrete placement. |