Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.
Inspection Status: Partial Pass
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 01/05/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
1-5-26: reinforcement for footings,column F4, and #5 hairpins around anchor zones verified per schedules located at S2.0& detail's 101-105-S3.0. Okay for concrete placement for slab at grade and at progress areas mentioned above. UFER 3/0 verified and located at north side of site. |
| 02/11/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Canceled |
2-11-26: canceled by contractor. |
| 02/12/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2-12-26: excavation/reinforcements at electrical/equipment pad & turndown footings/pad for metal building verified per plans. Okay for concrete placement. |
| 05/08/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Passed |
5-8-26: previously inspected & approved. |
| 12/16/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
12-16-25: reinforcement/excavation on 14 exterior footers verified per S2.0 details F1/F2. There were 8 -F2 & 6-F1 footers with each having 4-#4 hooked dowels. Okay for concrete placement at progress areas. |
| 12/17/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
12-17-25: reinforcement/excavation on 10-F3 footers verified per S2.0-footing schedule. Okay for concrete placement. |