Inspection Status: Partial Pass

Inspection History: COT - LCBU - Excavation/Rebar/Zoning 

Date Description Inspector Results Comments
01/05/2026 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 1-5-26: reinforcement for footings,column F4, and #5 hairpins around anchor zones verified per schedules located at S2.0& detail's 101-105-S3.0. Okay for concrete placement for slab at grade and at progress areas mentioned above. UFER 3/0 verified and located at north side of site.
02/11/2026 COT - LCBU - Excavation/Rebar/Zoning  Canceled 2-11-26: canceled by contractor.
02/12/2026 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 2-12-26: excavation/reinforcements at electrical/equipment pad & turndown footings/pad for metal building verified per plans. Okay for concrete placement.
05/08/2026 COT - LCBU - Excavation/Rebar/Zoning  Passed 5-8-26: previously inspected & approved.
12/16/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 12-16-25: reinforcement/excavation on 14 exterior footers verified per S2.0 details F1/F2. There were 8 -F2 & 6-F1 footers with each having 4-#4 hooked dowels. Okay for concrete placement at progress areas.
12/17/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 12-17-25: reinforcement/excavation on 10-F3 footers verified per S2.0-footing schedule. Okay for concrete placement.