Permit: TC-COM-0524-00906
Permit Details
Status:
Inspections Complete
Type:
Commercial Building
Address:
7655 S KOLB RD
Address NEW:
7655 S KOLB RD
Apply Date:
05/10/2024
Applicant:
Colton Lloyd
Description:
New construction of a building and the affiliated site work for the use as an office building for the Tucson Police Department
Permit Reviews
Permit Number - TC-COM-0524-00906
Permit Status: Inspections complete
Permit Description: New construction of a building and the affiliated site work for the use as an office building for the Tucson Police Department
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/21/2024 | COMMERCIAL REVIEW - LIMITED v.4 | 11/14/2024 | APPROVED |
| 03/16/2026 | COMMERCIAL REVIEW - FULL v.1 | N/A | IN REVIEW |
| 05/14/2024 | COMMERCIAL REVIEW - LIMITED v.1 | 06/04/2024 | REQUIRES RESUBMIT |
| 09/16/2024 | COMMERCIAL REVIEW - LIMITED v.3 | 10/01/2024 | REQUIRES RESUBMIT |
| 11/14/2024 | RESTAMP - COMMERCIAL v.1 | 11/15/2024 | APPROVED |
| 01/29/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/03/2026 | APPROVED |
| 06/24/2024 | COMMERCIAL REVIEW - LIMITED v.2 | 07/15/2024 | REQUIRES RESUBMIT |
| 02/10/2026 | SPECIAL INSPECTION REVIEW v.1 | 02/10/2026 | REQUIRES RESUBMIT |
| 03/02/2026 | SPECIAL INSPECTION REVIEW v.2 | 03/04/2026 | APPROVED |
| 05/01/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/06/2025 | APPROVED |
| 03/16/2026 | SPECIAL INSPECTION REVIEW v.1 | 03/17/2026 | APPROVED |
Conditions
Permit Number - TC-COM-0524-00906
Permit Status: Inspections complete
Permit Description: New construction of a building and the affiliated site work for the use as an office building for the Tucson Police Department
| Date | Description | Comments |
|---|---|---|
| 05/09/2025 | An intermediate Elevation Certificate is required PRIOR TO GRADING and/or PRE-SLAB INSPECTION. | |
| 07/12/2024 | Deferred submittal for Fabric Shade Canopy. Should this option be executed, Provide Fabric Shade Canopy drawings to include steel frame, steel columns, footing & shade. Provide the Shade Flame Spread Rating Index as well as the Fire Propagation Performance information as well as the Structural Drawings and Calculations prior to Building Final Inspection. | |
| 06/04/2024 | Masonry Inspection Report submittal review is required. | |
| 06/04/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
| 06/04/2024 | Post-Installed Anchor Inspection Report is required. | |
| 06/04/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 05/09/2025 | Submission of the final Elevation Certificate and completion of the Floodplain Use Permit is required PRIOR TO FINALING this permit. | |
| 05/14/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 06/04/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. | |
| 06/04/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
| 01/26/2026 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 06/04/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-COM-0524-00906
Permite Description: New construction of a building and the affiliated site work for the use as an office building for the Tucson Police Department
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/19/2025 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 12/19/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 12/19/2025 | COT - FCON - Fire - Final | N/A | Partial Pass | Key switch for gate still needs to be tested and a key for the Knox Box is still needed. |
| 06/03/2025 | COT - LCBU - Masonry Pregrout | N/A | Partial Pass | 6-3-25: cmu wall at Gridline B top out at 22' approved. |
| 07/14/2025 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | 7-14-25: above ceiling mep's in room's 114, 107 & 103 verified per plans-lans. Okay to close hard lid areas. |
| 08/04/2025 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | |
| 06/27/2025 | COT - LCEL - Electrical Progress | N/A | Partial Pass | All in wall electrical in place. Okay to proceed progress areas. 6/27/2025 |
| 08/06/2025 | COT - LCEL - Electrical Underground | N/A | Partial Pass | X2 1” Two light poles connected to ground box. Daisy chained to flag pole. 2” future solar to ground box also 1 1/4”future Ev charger. Okay to backfill progress areas. Shading required. 8/6/2025 |
| 06/25/2025 | COT - LCPL - Rough Soil | N/A | Partial Pass | Domestic water and DWV on test 114,106,107,108,109,103. 6/25/2025 |
| 05/01/2025 | COT - LCPL - Sewer | N/A | Partial Pass | 5/1/25: progress inspection for rough plumbing in room 104, ok to backfill. |
| 01/27/2026 | LCBU - Preslab and Floodplain Inspection | N/A | Not Ready |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-COM-0524-00906
Permit Description: New construction of a building and the affiliated site work for the use as an office building for the Tucson Police Department
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/05/2025 | COT - LCPL - Plumbing Intermediate | Passed | 5-5-25, underground plumbing verified as per approved plans. Okay to backfill with shading materials. | |
| 06/20/2025 | COT - HCBU - Roof Nailing | Passed | ||
| 06/25/2025 | COT - HCPL - Plumbing Intermediate | Passed | Domestic water and DWV on test 114,106,107,108,109,103. 6/25/2025 | |
| 01/27/2026 | COT - FCON - Fire - Final | Passed | ||
| 01/27/2026 | COT - LCBU - Masonry Pregrout | Passed | ||
| 01/27/2026 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 01/27/2026 | COT - LCEL - Electrical Intermediate | Passed | ||
| 01/27/2026 | COT - LCPL - Gas Pressure Test | Passed | ||
| 01/27/2026 | COT - LCEL - Electrical Progress | Passed | ||
| 01/27/2026 | COT - LCEL - Electrical Underground | Passed | ||
| 01/27/2026 | COT - LCPL - Rough Soil | Passed | ||
| 01/27/2026 | COT - LCPL - Sewer | Passed | ||
| 01/27/2026 | COT - LCEL - Grounding/Bonding | Passed | ||
| 01/27/2026 | COT - LCEL - Outdoor Lighting | Passed | ||
| 01/27/2026 | COT - LCPL - Yard Water Line | Passed | ||
| 01/27/2026 | COT - LCEL - Electrical Final | Passed | ||
| 01/27/2026 | COT - LCME - Mechanical Final | Passed | ||
| 01/27/2026 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. | |
| 01/28/2026 | TRSP - ROW - Final/Close-Out | Passed | All work performed within the right of way is now complete and a final right of way inspection was passed on December 23, 2025. | |
| 02/19/2026 | COT - LCPL - Plumbing Final | Passed | 2/19/26 pump installed and functioning properly | |
| 07/23/2026 | LCBU - Preslab and Floodplain Inspection | Passed | ||
| 07/23/2026 | COT - LCBU - Building Final | Passed | ||
| 07/23/2026 | COT - HCBU - CofO | Passed |