Parcel: 14122004W


Addresses:

7655 S KOLB RD


Inspection Status: Partial Pass

Inspection History: COT - LCEL - Electrical Underground 

Permit Number - TC-COM-0524-00906

Inspection Description - COT - LCEL - Electrical Underground 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
06/09/2025 COT - LCEL - Electrical Underground  Partial Pass 6-9-25: this is a framing progress inspection to include verification of hold-downs, metal framing screw-spacing, and anchor bolts. Framing construction is ongoing and will be inspected periodically.
06/12/2025 COT - LCEL - Electrical Underground  Partial Pass 6-12-25: verified trench depth for 4-electrical schedule 40 conduits (1-4", 1-3", 2-2")-okay to backfill approximately 100' of trench. Verified nailing at the decking above office areas together with h-25's 32" o.c., and 8" brackets and their required screws for metal framing/parapets. Okay to continue with installation of plywood to metal framing at progress areas.
06/17/2025 COT - LCEL - Electrical Underground  Partial Pass X2 2” schedule 40 for future solar from SES location heading south approximately 60’ okay to backfill progress areas. 6/17/2025
06/20/2025 COT - LCEL - Electrical Underground  Partial Pass X2 1 1/4” schedule 40 conduit for EV chargers heading south. X1 1 1/4” for EV charger heading East. X2 1” for light pole to light pole South ends.
Continuous 90 2” is for future solar. Approximately 70’. All at a 36” depth. Okay to backfill progress areas. Shading required. 6/20/2025
08/06/2025 COT - LCEL - Electrical Underground  Partial Pass X2 1” Two light poles connected to ground box. Daisy chained to flag pole. 2” future solar to ground box also 1 1/4”future Ev charger. Okay to backfill progress areas. Shading required. 8/6/2025
08/11/2025 COT - LCEL - Electrical Underground  Partial Pass 8-11-25: verified trench depth on 1-2" schedule 40 for future solar at south parking bays, 2-1 1/4" schedule 40 for future EV chargers at south parking bays. Okay to backfill progress areas.