Permit: TC-COM-0524-00906

Parcel: 14122004W


Addresses:

7655 S KOLB RD

Inspection Status: Passed

Inspection History: COT - LCBU - Masonry Pregrout 

Date Description Inspector Results Comments
01/27/2026 COT - LCBU - Masonry Pregrout  Passed
05/07/2025 COT - LCBU - Masonry Pregrout  Partial Pass 5/7/5/25: STEM-WALL AT CMU WALL PER APPROVED PLANS OK TO PROCEED WITH CONCRETE PLACEMENT.
05/20/2025 COT - LCBU - Masonry Pregrout  Partial Pass 5-20-25: reinforcement on CMU wall verified per approved plans. Okay to grout 1st lift at 4'.
05/22/2025 COT - LCBU - Masonry Pregrout  Partial Pass 5-22-25, reinforcement on CMU wall verified per plan. Okay to grout 2nd lift at 8'.
05/27/2025 COT - LCBU - Masonry Pregrout  Partial Pass 5-27-25: reinforcement for CMU walls verified per plans. Okay to grout 3rd lift at 12'.
05/29/2025 COT - LCBU - Masonry Pregrout  Partial Pass 5-29-25: exterior wall top out at 14' 8" top out and interior cmu wall at 16'(4th lift) each okay to grout. Reinforcement for column footing verified per plans-okay to pour.
05/30/2025 COT - LCBU - Masonry Pregrout  Partial Pass 5-30-25: reinforcement on CMU wall/gridline D at 20'-okay to grout 5th lift.
06/02/2025 COT - LCBU - Masonry Pregrout  Partial Pass 6-3-25: cmu wall at Gridline B top out at 22' approved.
06/04/2025 COT - LCBU - Masonry Pregrout  Partial Pass 6-4-25: reinforcement/excavation for 4 light pole cages verified per plans. Okay to pour concrete.
09/03/2025 COT - LCBU - Masonry Pregrout  Not Ready