Inspection Status: Passed
Inspection History: COT - LCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 01/27/2026 |
COT - LCBU - Masonry Pregrout |
|
Passed |
|
| 05/07/2025 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
5/7/5/25: STEM-WALL AT CMU WALL PER APPROVED PLANS OK TO PROCEED WITH CONCRETE PLACEMENT. |
| 05/20/2025 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
5-20-25: reinforcement on CMU wall verified per approved plans. Okay to grout 1st lift at 4'. |
| 05/22/2025 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
5-22-25, reinforcement on CMU wall verified per plan. Okay to grout 2nd lift at 8'. |
| 05/27/2025 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
5-27-25: reinforcement for CMU walls verified per plans. Okay to grout 3rd lift at 12'. |
| 05/29/2025 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
5-29-25: exterior wall top out at 14' 8" top out and interior cmu wall at 16'(4th lift) each okay to grout. Reinforcement for column footing verified per plans-okay to pour. |
| 05/30/2025 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
5-30-25: reinforcement on CMU wall/gridline D at 20'-okay to grout 5th lift. |
| 06/02/2025 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
6-3-25: cmu wall at Gridline B top out at 22' approved. |
| 06/04/2025 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
6-4-25: reinforcement/excavation for 4 light pole cages verified per plans. Okay to pour concrete. |
| 09/03/2025 |
COT - LCBU - Masonry Pregrout |
|
Not Ready |
|