Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0524-00906
Permit Details
Apply Date:
05/10/2024
Applicant:
Colton Lloyd
Description:
New construction of a building and the affiliated site work for the use as an office building for the Tucson Police Department
Permit Reviews
Permit Number - TC-COM-0524-00906
Permit Status: Issued
Permit Description: New construction of a building and the affiliated site work for the use as an office building for the Tucson Police Department
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/21/2024 | COMMERCIAL REVIEW - LIMITED v.4 | 11/14/2024 | APPROVED |
| 05/14/2024 | COMMERCIAL REVIEW - LIMITED v.1 | 06/04/2024 | REQUIRES RESUBMIT |
| 09/16/2024 | COMMERCIAL REVIEW - LIMITED v.3 | 10/01/2024 | REQUIRES RESUBMIT |
| 11/14/2024 | RESTAMP - COMMERCIAL v.1 | 11/15/2024 | APPROVED |
| 06/24/2024 | COMMERCIAL REVIEW - LIMITED v.2 | 07/15/2024 | REQUIRES RESUBMIT |
| 05/01/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/06/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0524-00906
Permit Status: Issued
Permit Description: New construction of a building and the affiliated site work for the use as an office building for the Tucson Police Department
Total Outstanding Activity Conditions - 9
| Date | Name |
|---|---|
| 05/09/2025 | Submission of the final Elevation Certificate and completion of the Floodplain Use Permit is required PRIOR TO FINALING this permit. |
| 06/03/2024 | This project requires the completion of a Fire Construction Permit PRIOR TO FINALING this permit. |
| 06/04/2024 | Masonry Inspection Report submittal review is required. |
| 06/04/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. |
| 06/04/2024 | Post-Installed Anchor Inspection Report is required. |
| 06/04/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
| 06/04/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. |
| 06/04/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
| 07/12/2024 | Deferred submittal for Fabric Shade Canopy. Should this option be executed, Provide Fabric Shade Canopy drawings to include steel frame, steel columns, footing & shade. Provide the Shade Flame Spread Rating Index as well as the Fire Propagation Performance information as well as the Structural Drawings and Calculations prior to Building Final Inspection. |
Conditions
Permit Number - TC-COM-0524-00906
Permit Status: Issued
Permit Description: New construction of a building and the affiliated site work for the use as an office building for the Tucson Police Department
| Date | Description | Comments |
|---|---|---|
| 05/09/2025 | An intermediate Elevation Certificate is required PRIOR TO GRADING and/or PRE-SLAB INSPECTION. | |
| 05/14/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 06/04/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0524-00906
Permite Description: New construction of a building and the affiliated site work for the use as an office building for the Tucson Police Department
Total Outstanding Inspections - 13
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/01/2025 | COT - LCPL - Sewer | N/A | Partial Pass | 5/1/25: progress inspection for rough plumbing in room 104, ok to backfill. |
| 05/12/2025 | COT - LCPL - Yard Water Line | N/A | Partial Pass | 5/7/25: 10' stretch of 2" copper for water line under pressure. Stubbing under exterior wall. Ok to proceed. 5/12/25: 120' of 2" soft copper type K per plans. Per approved plans. Proper burial depth and tracer wire installed. Ok to proceed with backfill at progress location. |
| 05/14/2025 | LCBU - Preslab and Floodplain Inspection | N/A | Partial Pass | 5-14-25, verified that vapor in place together with reinforcement per plans. Per contractor, a civil engineer verified elevation to one-hundredth of an inch. However, their 3rd party (Meridian) will inspect after pour and complete the rest of the required paperwork. Okay to pour at own risk pending floodplain certification. Note: submit 3rd party and floodplain reports as soon as possible as it's required prior to building final. |
| 06/25/2025 | COT - LCPL - Rough Soil | N/A | Partial Pass | Domestic water and DWV on test 114,106,107,108,109,103. 6/25/2025 |
| 06/27/2025 | COT - LCEL - Electrical Progress | N/A | Partial Pass | All in wall electrical in place. Okay to proceed progress areas. 6/27/2025 |
| 08/04/2025 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | |
| 08/06/2025 | COT - LCEL - Electrical Underground | N/A | Partial Pass | X2 1” Two light poles connected to ground box. Daisy chained to flag pole. 2” future solar to ground box also 1 1/4”future Ev charger. Okay to backfill progress areas. Shading required. 8/6/2025 |
| 07/14/2025 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | 7-14-25: above ceiling mep's in room's 114, 107 & 103 verified per plans-lans. Okay to close hard lid areas. |
| 06/03/2025 | COT - LCBU - Masonry Pregrout | N/A | Partial Pass | 6-3-25: cmu wall at Gridline B top out at 22' approved. |
| 12/19/2025 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 12/19/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 12/19/2025 | COT - FCON - Fire - Final | N/A | Partial Pass | Key switch for gate still needs to be tested and a key for the Knox Box is still needed. |
| 12/19/2025 | COT - LCBU - Building Final | N/A | Re-inspection required | 12/19/25: conducted a general walk through of the entire building, receptacle at roof for HVAC servicing not energized, receptacle in ada bathroom south east corner not energized, all disconnect boxes must be labeled, vertical grab bars at ADA shower required, all exterior plastic piping must be coated for UV protection, utilities closet not ready (booster pump must be installed) properly support all piping vertically and horizontally in utility room, all ceiling tiles must be installed, extension bar at roof access required on ladder, seal all ductwork at RTUs under sun shade for duct flex connector, properly secure conduit at exterior disconnect box, wiring at conduit for gate motor must be installed at time of inspection, site work is incomplete (engineering final not ready), fire final required prior to issuance of building final, R.O.W final required prior to issuance of building final. Please go through all required conditions and ensure they are uploaded to your permit prior to calling in building finals. Backflow preventer must be replaced for correct size. Please call in all inspections on permit card. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0524-00906
Permit Description: New construction of a building and the affiliated site work for the use as an office building for the Tucson Police Department
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/05/2025 | COT - LCPL - Plumbing Intermediate | Passed | 5-5-25, underground plumbing verified as per approved plans. Okay to backfill with shading materials. | |
| 06/20/2025 | COT - HCBU - Roof Nailing | Passed | ||
| 06/25/2025 | COT - HCPL - Plumbing Intermediate | Passed | Domestic water and DWV on test 114,106,107,108,109,103. 6/25/2025 |