Permit: TC-COM-0524-00779
Permit Details
Status:
In Review
Type:
Commercial Building
Address:
530 E VALENCIA RD
Address NEW:
530 E VALENCIA RD
Apply Date:
05/02/2024
Applicant:
Avery Hall
Description:
Rev.1: 06/10/2026 New high speed diesel canopy with 3 pumps with existing convenience store and fuel canopy with 10 pumps
Permit Reviews
Permit Number - TC-COM-0524-00779
Permit Status: In review
Permit Description: Rev.1: 06/10/2026
New high speed diesel canopy with 3 pumps with existing convenience store and fuel canopy with 10 pumps
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/08/2024 | COMMERCIAL REVIEW - FULL v.1 | 06/10/2024 | REQUIRES RESUBMIT |
| 12/16/2024 | COMMERCIAL REVIEW - FULL v.3 | 01/10/2025 | REQUIRES RESUBMIT |
| 06/17/2025 | RESTAMP - COMMERCIAL v.1 | 06/18/2025 | APPROVED |
| 06/10/2026 | COMMERCIAL REVIEW - FULL v.1 | N/A | IN REVIEW |
| 06/10/2025 | COMMERCIAL REVIEW - FULL v.6 | 06/17/2025 | APPROVED |
| 01/14/2025 | COMMERCIAL REVIEW - FULL v.4 | 02/05/2025 | REQUIRES RESUBMIT |
| 12/14/2024 | COMMERCIAL REVIEW - FULL v.2 | 12/14/2024 | REQUIRES RESUBMIT |
| 02/10/2025 | COMMERCIAL REVIEW - FULL v.5 | 02/26/2025 | REQUIRES RESUBMIT |
| 12/10/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/18/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0524-00779
Permit Status: In review
Permit Description: Rev.1: 06/10/2026
New high speed diesel canopy with 3 pumps with existing convenience store and fuel canopy with 10 pumps
Total Outstanding Activity Conditions - 9
| Date | Name |
|---|---|
| 02/14/2025 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. |
| 02/14/2025 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
| 02/14/2025 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 02/14/2025 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 02/14/2025 | Masonry Inspection Report submittal review is required. |
| 02/14/2025 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. |
| 02/14/2025 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
| 12/11/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 12/11/2025 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
Conditions
Permit Number - TC-COM-0524-00779
Permit Status: In review
Permit Description: Rev.1: 06/10/2026
New high speed diesel canopy with 3 pumps with existing convenience store and fuel canopy with 10 pumps
| Date | Description | Comments |
|---|---|---|
| 05/08/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 12/14/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 02/14/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 02/14/2025 | STATE FIRE MARSHAL INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION |
Outstanding Inspections
Permit Status: In Review
Permit Number: TC-COM-0524-00779
Permite Description: Rev.1: 06/10/2026
New high speed diesel canopy with 3 pumps with existing convenience store and fuel canopy with 10 pumps
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/18/2026 | COT - HCBU - Stem Wall/Retaining Wall | N/A | Not Ready | Inspection was for trash enclosure. Referred to site team. 3/18/2026 |
| 04/21/2026 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Re-inspection required | 4-21-26: per NEC, Table 300.5 minimal trench depth (cover) for a 1" Schedule 40 electrical conduit is 18" in residential, commercial, or industrial applications from top of conduit to finished grade. Reschedule this inspection when ready. Okay for concrete placement at light pole cage east of the trash enclosure. |
| 04/24/2026 | COT - HCEL - Grounding/Bonding | N/A | Partial Pass | 4-24-26: verified bonding at canopy. |
| 05/07/2026 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 5-7-26: 1" schedule 40 electrical conduits for light poles approved. Okay to backfill approximately 500' of open trench using shading materials. |
| 04/30/2026 | COT - HCBU - Preslab | N/A | Partial Pass | 4-30-26: reinforcement for fuel tank mat with #4's @12" o.c. approved. Okay for concrete placement. |
| 04/15/2026 | COT - HCEL - Outdoor Lighting | N/A | Partial Pass | 4-15-26: approximately 300' of main water line verified under test. Line stems from the air/water located on north side and runs south where there are 2 hose bibs and continues southeast side of building. Okay to backfill progress areas using shading materials. |
| 06/08/2026 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 6-8-26: pending Load calcs required for new circuit tied to incorrect panels -revision required. |
| 06/05/2026 | COT - HCBU - Building Final | N/A | Re-inspection required | 6/5/26: all EMT explosion proof fittings shall be opened to verify Chico sealant, Load calcs required for new circuit tied to incorrect panels (revision required), panel schedule must be corrected and legible, all finals shall be called in, conditions must be satisfied, state fire marshal approval required prior to final. |
Completed Inspections
Permit Status: In Review
Permit Number: TC-COM-0524-00779
Permit Description: Rev.1: 06/10/2026
New high speed diesel canopy with 3 pumps with existing convenience store and fuel canopy with 10 pumps
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/05/2026 | COT - FCON - Fire - Final | Passed | ||
| 06/08/2026 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
| 06/08/2026 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
| 06/08/2026 | COT - HCBU - Framing | Passed | ||
| 06/08/2026 | COT - HCEL - Grounding/Bonding | Passed | ||
| 06/08/2026 | COT - HCEL - Electrical Underground | Passed | ||
| 06/08/2026 | COT - HCBU - Preslab | Passed | ||
| 06/08/2026 | TRSP - ROW - Final/Close-Out | Passed | ||
| 06/11/2026 | COT - HCEL - Electrical Intermediate | Passed | 6-11-26: electrical intermediates approved. | |
| 06/11/2026 | COT - HCEL - Electrical Final | Passed | 6-11-26: electrical final approved. | |
| 06/11/2026 | ENGR Engineering Final | Passed |