Inspection Status: Partial Pass
Inspection History: COT - HCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 03/09/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
3-9-26: excavation/reinforcement on 3 spread footings for canopy verified per plans with 8-#5's top & bottom. Okay for concrete placement at progress areas. |
| 04/24/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
4-24-26: okay to pour mat at canopy. |
| 04/30/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
4-30-26: reinforcement for fuel tank mat with #4's @12" o.c. approved. Okay for concrete placement. |
| 06/08/2026 |
COT - HCBU - Preslab |
|
Passed |
|