Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 03/12/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
3-12-26: verified trench depth at over 2' containing 15 plus- 3/4" & 1" secondary electrical conduits. Conduits stem from the southeast corner of site and run approximately 90' in a northwest direction. Okay to backfill progress areas. |
|
COT - HCEL - Electrical Underground |
|
Partial Pass |
4-6-26: verified 15 schedule 40 electrical conduits consisting of 5-1" & 10-3/4" secondary conduits that extend from a south direction and run northwest to canopy. Okay to backfill approximately 50' of open trench using shading materials. |
| 04/21/2026 |
COT - HCEL - Electrical Underground |
|
Re-inspection required |
4-21-26: light pole conduit inspection -per NEC, Table 300.5 minimal trench depth (cover) for a 1" Schedule 40 electrical conduit is 18" in residential, commercial, or industrial applications from top of conduit to finished grade. Reschedule this inspection when ready. Okay for concrete placement at light pole cage east of the trash enclosure. |
| 05/07/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
5-7-26: 1" schedule 40 electrical conduits for light poles approved. Okay to backfill approximately 500' of open trench using shading materials. |
| 06/08/2026 |
COT - HCEL - Electrical Underground |
|
Passed |
|