Permit Details

Status:
Complete
Type:
Commercial Building
Address:
3476 S KINO PW
Address NEW:
3476 S KINO PW
Apply Date:
04/25/2023
Applicant:
Charles Romero
Description:
New Outpatient Clinic

Permit Reviews

Permit Number - TC-COM-0423-01135
Permit Status: Complete
Permit Description: New Outpatient Clinic
Start Date Submittal Complete Date Status  
08/30/2023 RESTAMP - COMMERCIAL v.1 08/31/2023 APPROVED Review Details
11/03/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/13/2023 APPROVED Review Details
07/10/2023 COMMERCIAL REVIEW - FULL v.2 07/19/2023 REQUIRES RESUBMIT Review Details
07/17/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/22/2024 APPROVED Review Details
07/24/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/31/2024 APPROVED Review Details
08/28/2023 COMMERCIAL REVIEW - FULL v.3 08/30/2023 APPROVED Review Details
05/01/2023 COMMERCIAL REVIEW - FULL v.1 07/06/2023 REQUIRES RESUBMIT Review Details
09/26/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/26/2024 APPROVED Review Details

Conditions

Permit Number - TC-COM-0423-01135
Permit Status: Complete
Permit Description: New Outpatient Clinic
Date Description Comments
07/04/2024 AIR BALANCING REPORT IS REQUIRED.
07/04/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
07/04/2024 Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit.
07/04/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
07/04/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
07/04/2024 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
07/04/2024 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
07/04/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
07/04/2024 Masonry Inspection Report submittal review is required.
07/04/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
07/04/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
07/04/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0423-01135
Permite Description: New Outpatient Clinic
Total Outstanding Inspections - 9
Last Inspection Date Description Inspector Results Comments
10/16/2023 COT - LCPL - Sewer N/A Partial Pass Partial pass. All plumbing underground under test okay to backfill. Shading is required. 4” stubbed out north center of building pending point of connection to the HCS. 10/16/2023
10/13/2023 COT - HCBU - Masonry Pregrout N/A Partial Pass 1st lift, South and West walls.
10/16/2023 COT - HCPL - Plumbing Progress N/A Partial Pass Partial pass. All plumbing underground under test okay to backfill. Shading is required. 4” stubbed out north center of building pending point of connection to the HCS. 10/16/2023
10/11/2023 COT - HCEL - Electrical Progress N/A Partial Pass Approximately 50 feet from transformer on northside of lot to mid span east side of building
10/5/23 partial for temp power conduit from transformer, ok to cover
10/11/23: (1) 2 1/2" conduit for cox low voltage ok to back fill, (3) 4" conduit for extension to TERM CAN ok to back fill, temp power conduit from transformer ok to cover.
12/15/2023 COT - HCBU - Framing N/A Not Ready
10/17/2023 COT - HCEL - Electrical Underground N/A Partial Pass 10/17/23 all under slab ok to cover
09/21/2023 COT - HCBU - Building Progress N/A Partial Pass 9/21/23: sewer per plan stub extension ok to backfill
09/27/2023 COT - HCBU - Preslab N/A Partial Pass 9/27/23: interior footings and exterior footings reinforcement per plan ok to pour.
07/16/2024 COT - BULD - SWG Clearance N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0423-01135
Permit Description: New Outpatient Clinic
Total Completed Inspections - 29
Date Description Inspector Results Comments
09/27/2023 COT - HCEL - Grounding/Bonding Passed 9/27/25: grounding/bonding per plan
10/20/2023 COT - LCPL - Sewer Passed
11/14/2023 COT - HCBU - Masonry Pregrout Passed
12/15/2023 COT - HCBU - Roof Nailing Passed
02/09/2024 COT - HCME - Mechanical Progress Passed
02/09/2024 COT - HCPL - Plumbing Progress Passed
02/09/2024 COT - HCEL - Electrical Progress Passed
02/16/2024 COT - HCBU - Framing Passed
02/27/2024 COT - HCPL - Plumbing Intermediate Passed
02/27/2024 COT - HCPL - Plumbing Above Ceiling Passed
04/30/2024 BULD - Electrical Clearance Passed 4/30/24: ECO for OWNER meter at 3476 S KINO PW.
05/13/2024 COT - HCME - Mechanical Above Ceiling Passed
05/16/2024 COT - HCEL - Electrical Underground Passed
05/16/2024 COT - HCEL - Electrical Intermediate Passed
05/16/2024 COT - HCBU - Building Above Ceiling Passed 5/16/24: above ceiling complete ok to proceed.
05/16/2024 COT - HCEL - Electrical Above Ceiling Passed 5/16/24: electrical above ceiling passed. Ok to proceed
05/16/2024 COT - HCBU - Building Progress Passed
07/08/2024 COT - HCME - Venting Passed
07/17/2024 COT - HCEL - Electrical Final Passed
07/17/2024 COT - HCME - Mechanical Final Passed
07/17/2024 COT - HCPL - Plumbing Final Passed
07/16/2024 COT - HCBU - Preslab Passed
07/18/2024 COT - FCON - Sprinkler - Final Passed
07/18/2024 COT - FCON - Fire - Final Passed
07/18/2024 COT - FCON - Alarm - Final Passed
07/24/2024 ENGR Engineering Final Passed
07/24/2024 TRSP - ROW - Final/Close-Out Passed
07/25/2024 COT - HCBU - CofO Passed 7/17/24: pending special inspection reports, pending air balance report and water sterilization report.
7/25/24: ok for CofO
07/25/2024 COT - HCBU - Building Final Passed 7/17/24: pending special inspection reports, pending air balance report and water sterilization report.
7/25/24: ok for CofO