Permit: TC-COM-0423-00982
Permit Details
Apply Date:
04/06/2023
Applicant:
Evan Bowen
Description:
THIS PORTION OF THE PROJECT CONSISTS OF ONLY THE TENANT IMPROVEMENT (TI) PACKAGE FOR A PRE-ENGINEERED METAL BUIDLING. SEPARATE PACKAGES FOR THE FOUNDATION, SHELL AND DEVELOPEMENT PACKAGE ARE UNDER SEPARATE PERMITS.
Permit Reviews
Permit Number - TC-COM-0423-00982
Permit Status: Complete
Permit Description: THIS PORTION OF THE PROJECT CONSISTS OF ONLY THE TENANT IMPROVEMENT (TI) PACKAGE FOR A PRE-ENGINEERED METAL BUIDLING. SEPARATE PACKAGES FOR THE FOUNDATION, SHELL AND DEVELOPEMENT PACKAGE ARE UNDER SEPARATE PERMITS.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/11/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/14/2024 | REQUIRES RESUBMIT |
06/24/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/25/2024 | APPROVED |
07/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 07/23/2024 | APPROVED |
07/14/2023 | COMMERCIAL REVIEW - FULL v.2 | 07/21/2023 | REQUIRES RESUBMIT |
08/11/2023 | RESTAMP - COMMERCIAL v.1 | 08/15/2023 | APPROVED |
04/10/2023 | COMMERCIAL REVIEW - FULL v.1 | 05/09/2023 | REQUIRES RESUBMIT |
07/16/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/17/2024 | REQUIRES RESUBMIT |
08/07/2023 | COMMERCIAL REVIEW - FULL v.3 | 08/11/2023 | APPROVED |
Conditions
Permit Number - TC-COM-0423-00982
Permit Status: Complete
Permit Description: THIS PORTION OF THE PROJECT CONSISTS OF ONLY THE TENANT IMPROVEMENT (TI) PACKAGE FOR A PRE-ENGINEERED METAL BUIDLING. SEPARATE PACKAGES FOR THE FOUNDATION, SHELL AND DEVELOPEMENT PACKAGE ARE UNDER SEPARATE PERMITS.
Date | Description | Comments |
---|---|---|
06/10/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
06/10/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
06/10/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
06/10/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
06/25/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
06/25/2024 | Masonry Inspection Report submittal review is required. | |
06/25/2024 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. | |
06/25/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
06/14/2024 | STATE FIRE MARSHAL INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0423-00982
Permite Description: THIS PORTION OF THE PROJECT CONSISTS OF ONLY THE TENANT IMPROVEMENT (TI) PACKAGE FOR A PRE-ENGINEERED METAL BUIDLING. SEPARATE PACKAGES FOR THE FOUNDATION, SHELL AND DEVELOPEMENT PACKAGE ARE UNDER SEPARATE PERMITS.
Total Outstanding Inspections - 10
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/28/2024 | COT - HCBU - Framing | N/A | Partial Pass | |
06/05/2024 | COT - HCME - Mechanical Progress | N/A | Partial Pass | 6/5/24: kitchen grease hood smoke test passed at first floor. Ok to wrap progress areas. |
05/30/2024 | COT - HCBU - Building Progress | N/A | Not Ready | |
COT - FCON - Fire - Final | N/A | Not Ready | ||
06/21/2024 | COT - HCEL - Electrical Final | N/A | Partial Pass | 6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 |
06/21/2024 | COT - HCEL - Outdoor Lighting | N/A | Partial Pass | 6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 |
06/21/2024 | COT - HCME - Mechanical Final | N/A | Partial Pass | 6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 |
06/21/2024 | COT - HCPL - Plumbing Final | N/A | Partial Pass | 6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 |
07/12/2024 | ENGR Engineering Final | N/A | Not Ready | The contract is still working on this site at various locations and one need to have all work completed prior to scheduling this inspection since this inspection is for a Temporary Certificate of Occupancy for the school. Also, the retention detention basin on the site is holding water past the 12 hour maximum limit, and will need to be checked by the engineer of record. I have advised BFL do you have the engineer of record look at the site and come up with a solution that will help eliminate all of the water within the 12 hour maximum limit. |
06/21/2024 | COT - HCBU - Building Final | N/A | Partial Pass | 6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0423-00982
Permit Description: THIS PORTION OF THE PROJECT CONSISTS OF ONLY THE TENANT IMPROVEMENT (TI) PACKAGE FOR A PRE-ENGINEERED METAL BUIDLING. SEPARATE PACKAGES FOR THE FOUNDATION, SHELL AND DEVELOPEMENT PACKAGE ARE UNDER SEPARATE PERMITS.
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/05/2024 | COT - HCPL - Gas Pressure Test | Passed | ||
05/03/2024 | BULD - Electrical Clearance | Passed | 3300 s Park Ave Unit 2 ECO TEP CLEARANCE | |
05/03/2024 | COT - HCBU - Preslab | Passed | ||
05/03/2024 | COT - HCEL - Electrical Underground | Passed | ||
05/03/2024 | COT - HCBU - Roof Nailing | Passed | ||
05/03/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
05/03/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
05/03/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
05/15/2024 | COT - HCBU - Framing | Passed | ||
05/15/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
05/22/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
05/22/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
06/21/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 |
|
06/21/2024 | COT - HCBU - Building Above Ceiling | Passed | Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 |
|
06/21/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
06/21/2024 | COT - HCEL - Electrical Above Ceiling | Passed | Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 |
|
06/26/2024 | COT - BULD - SWG Clearance | Passed | 6/26/24: SWG Clearance for meter tag | |
06/26/2024 | COT - HCPL - Gas Final | Passed | ||
06/26/2024 | COT - HCPL - Plumbing Progress | Passed | ||
06/26/2024 | COT - HCEL - Electrical Progress | Passed | ||
06/26/2024 | COT - HCME - Mechanical Progress | Passed | ||
06/26/2024 | COT - HCBU - Building Progress | Passed | ||
07/01/2024 | COT - FCON - Fire - Final | Passed | ||
07/11/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
07/11/2024 | COT - HCEL - Electrical Final | Passed | ||
07/11/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
07/11/2024 | COT - HCME - Mechanical Final | Passed | ||
07/11/2024 | COT - HCPL - Plumbing Final | Passed | ||
07/19/2024 | ENGR Engineering Final | Passed | ||
07/19/2024 | COT - HCBU - Building Final | Passed | 6/7/24: progress inspection on offices first floor north east for finals. ADA requirements not met at bathrooms. 6/10/24: progress inspection on offices first floor south west for finals. ADA requirements not met at bathrooms 6/11/24: Restrooms at first floor passed. Pending ADA approved restroom signs at Final 6/14/24: 127(penetrations at 2nd floor decking need to be sealed, receptacle not functioning) ,128(missing hanger at water line and missing cover for shut-off valve) 6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 6/26/24: OK FOR TCO LEVEL 1 6/25/24: will be called in with T.I final. Pending fire for engineering final for shell permit. 7/11/24: Ok for LEVEL 4 TCO 7/19/24: ok For CofO |
|
07/19/2024 | COT - HCBU - CofO | Passed | 6/7/24: progress inspection on offices first floor north east for finals. ADA requirements not met at bathrooms. 6/10/24: progress inspection on offices first floor south west for finals. ADA requirements not met at bathrooms 6/11/24: Restrooms at first floor passed. Pending ADA approved restroom signs at Final 6/14/24: 127(penetrations at 2nd floor decking need to be sealed, receptacle not functioning) ,128(missing hanger at water line and missing cover for shut-off valve) 6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 6/26/24: OK FOR TCO LEVEL 1 6/25/24: will be called in with T.I final. Pending fire for engineering final for shell permit. 7/11/24: Ok for LEVEL 4 TCO 7/19/24: ok For CofO |