Inspection Status: Partial Pass

Inspection History: COT - HCEL - Electrical Intermediate

Date Description Inspector Results Comments
01/08/2024 COT - HCEL - Electrical Intermediate Partial Pass Electrical rough CL A-E first floor ok to one side
01/10/2024 COT - HCEL - Electrical Intermediate Partial Pass Electrical rough CL A-E first floor ok to one side
Electrical rough CL E-J first floor OK to one side
02/21/2024 COT - HCEL - Electrical Intermediate Not Ready
02/23/2024 COT - HCEL - Electrical Intermediate Partial Pass Electrical rough CL A-E first floor ok to one side
Electrical rough CL E-J first floor OK to one side
2/23/24: Electrical In wall intermediate first floor passed ok to proceed.
02/28/2024 COT - HCEL - Electrical Intermediate Partial Pass
03/13/2024 COT - HCEL - Electrical Intermediate Partial Pass
03/18/2024 COT - HCEL - Electrical Intermediate Partial Pass Electrical rough CL A-E first floor ok to one side
Electrical rough CL E-J first floor OK to one side
2/23/24: Electrical In wall intermediate first floor passed ok to proceed.
2/28/24 electrical in wall intermediate second floor column line A to H
3/13/2 first floor kitchen walls ok to insulate
3/18/24: second floor electrical intermediate Column Line H-J