Inspection Status: Partial Pass

Inspection History: COT - HCME - Mechanical Final 

Permit Number - TC-COM-0423-00982

Inspection Description - COT - HCME - Mechanical Final 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
06/07/2024 COT - HCME - Mechanical Final  Partial Pass 6/7/24: progress inspection on offices first floor north east for finals. ADA requirements not met at bathrooms.
06/10/2024 COT - HCME - Mechanical Final  Partial Pass 6/7/24: progress inspection on offices first floor north east for finals. ADA requirements not met at bathrooms.
6/10/24: progress inspection on offices first floor south west for finals. ADA requirements not met at bathrooms
06/11/2024 COT - HCME - Mechanical Final  Partial Pass 6/7/24: progress inspection on offices first floor north east for finals. ADA requirements not met at bathrooms.
6/10/24: progress inspection on offices first floor south west for finals. ADA requirements not met at bathrooms
6/11/24: Restrooms at first floor passed. Pending ADA approved restroom signs at Final
06/14/2024 COT - HCME - Mechanical Final  Partial Pass 6/7/24: progress inspection on offices first floor north east for finals. ADA requirements not met at bathrooms.
6/10/24: progress inspection on offices first floor south west for finals. ADA requirements not met at bathrooms
6/11/24: Restrooms at first floor passed. Pending ADA approved restroom signs at Final
6/14/24: 127(penetrations at 2nd floor decking need to be sealed, receptacle not functioning) ,128(missing hanger at water line and missing cover for shut-off valve)
06/21/2024 COT - HCME - Mechanical Final  Partial Pass 6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131.
SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west.
Level 1 TCO FOR ROOM #152
06/26/2024 COT - HCME - Mechanical Final  Partial Pass 6/14/24: 127(penetrations at 2nd floor decking need to be sealed, receptacle not functioning) ,128(missing hanger at water line and missing cover for shut-off valve)


6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131.
SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west.
Level 1 TCO FOR ROOM #152
6/26/24: OK FOR TCO LEVEL 1
07/01/2024 COT - HCME - Mechanical Final  Not Ready
07/11/2024 COT - HCME - Mechanical Final  Passed