Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Final
Permit Number - TC-COM-0423-00982
Inspection Description - COT - HCBU - Building Final
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/07/2024 | COT - HCBU - Building Final | Partial Pass | 6/7/24: progress inspection on offices first floor north east for finals. ADA requirements not met at bathrooms. | |
06/10/2024 | COT - HCBU - Building Final | Partial Pass | 6/7/24: progress inspection on offices first floor north east for finals. ADA requirements not met at bathrooms. 6/10/24: progress inspection on offices first floor south west for finals. ADA requirements not met at bathrooms |
|
06/11/2024 | COT - HCBU - Building Final | Partial Pass | 6/7/24: progress inspection on offices first floor north east for finals. ADA requirements not met at bathrooms. 6/10/24: progress inspection on offices first floor south west for finals. ADA requirements not met at bathrooms 6/11/24: Restrooms at first floor passed. Pending ADA approved restroom signs at Final |
|
06/14/2024 | COT - HCBU - Building Final | Partial Pass | 6/7/24: progress inspection on offices first floor north east for finals. ADA requirements not met at bathrooms. 6/10/24: progress inspection on offices first floor south west for finals. ADA requirements not met at bathrooms 6/11/24: Restrooms at first floor passed. Pending ADA approved restroom signs at Final 6/14/24: 127(penetrations at 2nd floor decking need to be sealed, receptacle not functioning) ,128(missing hanger at water line and missing cover for shut-off valve) |
|
06/21/2024 | COT - HCBU - Building Final | Partial Pass | 6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 |
|
06/26/2024 | COT - HCBU - Building Final | Partial Pass | 6/14/24: 127(penetrations at 2nd floor decking need to be sealed, receptacle not functioning) ,128(missing hanger at water line and missing cover for shut-off valve) 6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 6/26/24: OK FOR TCO LEVEL 1 |
|
07/01/2024 | COT - HCBU - Building Final | Not Ready | ||
07/11/2024 | COT - HCBU - Building Final | Partial Pass | 6/7/24: progress inspection on offices first floor north east for finals. ADA requirements not met at bathrooms. 6/10/24: progress inspection on offices first floor south west for finals. ADA requirements not met at bathrooms 6/11/24: Restrooms at first floor passed. Pending ADA approved restroom signs at Final 6/14/24: 127(penetrations at 2nd floor decking need to be sealed, receptacle not functioning) ,128(missing hanger at water line and missing cover for shut-off valve) 6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 6/26/24: OK FOR TCO LEVEL 1 6/25/24: will be called in with T.I final. Pending fire for engineering final for shell permit. 7/11/24: Ok for LEVEL 4 TCO |
|
07/19/2024 | COT - HCBU - Building Final | Passed | 6/7/24: progress inspection on offices first floor north east for finals. ADA requirements not met at bathrooms. 6/10/24: progress inspection on offices first floor south west for finals. ADA requirements not met at bathrooms 6/11/24: Restrooms at first floor passed. Pending ADA approved restroom signs at Final 6/14/24: 127(penetrations at 2nd floor decking need to be sealed, receptacle not functioning) ,128(missing hanger at water line and missing cover for shut-off valve) 6/21/2024 partial pass. Room number corridor 100 north and south. 101, 150, 151, 152, 156, 146, 147, 145 and 135, 124, 124B, 126A, 125, 130, AND 131. SECOND FLOOR. 203, 204, 207, 210, 211, 237, 236, 235, 234, 223, 232, 233, 231, 225, 219, 218, 217, 212, 213, 214, 214A, 215, 220A, 218A, 220, 222, 221, 225, Corridor 200 main, Middle East, west. Level 1 TCO FOR ROOM #152 6/26/24: OK FOR TCO LEVEL 1 6/25/24: will be called in with T.I final. Pending fire for engineering final for shell permit. 7/11/24: Ok for LEVEL 4 TCO 7/19/24: ok For CofO |